Registering Property in Bangladesh, Chittagong
BUILDING A WAREHOUSE
Data as of: January 2006
City: Chittagong
Registration Requirements:
| Time to complete: | 7 days |
| Cost to complete: | BDT 1,200 |
| Comment: | |
| Time to complete: | 3 days |
| Cost to complete: | BDT 500 |
| Comment: | |
| Time to complete: | 3 days |
| Cost to complete: | BDT 300 |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | BDT 1,500 |
| Comment: | |
| Time to complete: | 60 days |
| Cost to complete: | BDT 5,000 |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | BDT 10,000 |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 20 days |
| Cost to complete: | BDT 8,500 |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | BDT 7,500 |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | BDT 700 |
| Comment: | |
| Note: Procedures sometimes take place simultaneously. Instances of this are marked with an asterisk (*).
|