Dealing with Licenses in Khulna, Bangladesh

BUILDING A WAREHOUSE
Data as of: January 2006
City: Khulna

Registration Requirements:
Procedure 1Obtain planning permission from Khulna Development Authority
Time to complete:45 days
Cost to complete:BDT 4500
Comment:
Procedure 2Obtain a set of design conditions and a plot map from the Khulna Development Authority
Time to complete:7 days
Cost to complete:no charge
Comment:
Procedure 3Obtain certificate of ownership from Tahsil Office
Time to complete:3 days
Cost to complete:no charge
Comment:
Procedure 4Obtain project clearance from Department of Environment
Time to complete:30 days
Cost to complete:no charge
Comment:
Procedure 5Obtain project clearance from Civil Defense Department (Fire Service Dept)
Time to complete:90 days
Cost to complete:no charge
Comment:
Procedure 6Receive pre-construction inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 7Receive excavation work inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 8Receive foundations work inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 9Obtain electricity connection
Time to complete:30 days
Cost to complete:BDT 15000
Comment:
Procedure 10Receive elecrticiy inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 11Obtain water and sewerage connection
Time to complete:3 days
Cost to complete:BDT 1500
Comment:
Procedure 12Obtain fixed telephone line
Time to complete:15 days
Cost to complete:BDT 7400
Comment:
Procedure 13Obtain occupancy permit
Time to complete:10 days
Cost to complete:no charge
Comment:
Note: Procedures sometimes take place simultaneously. Instances of this are marked with an asterisk (*).