Dealing with Construction Permits in Pakistan
The table below summarizes the procedures, time, and costs to build a warehouse in Pakistan.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Pakistan.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain letter from concerned authority confirming the land title | 30 days | no charge |
| 2 | Obtain a building permit | 60 days | PKR 140,000 |
| 3 | Notify the Karachi Building Control Authority (KBCA) in writing of the completion of foundations | 1 day | no charge |
| 4 | Receive foundations work inspection from the Karachi Building Control Authority (KBCA) | 15 days | no charge |
| 5 | Request electricity connection | 75 days | PKR 228,000 |
| *6 | Request telephone connection | 45 days | PKR 4,150 |
| *7 | Obtain copy of property tax valuation and copy of the certificate from the tax authorities | 30 days | no charge |
| 8 | Receive inspection from the Excise and Taxation department | 1 day | no charge |
| *9 | Request water and sewerage connection | 60 days | PKR 90,000 |
| 10 | Apply for occupancy permit and request final inspection | 1 day | no charge |
| *11 | Receive final inspection | 1 day | no charge |
| 12 | Receive completion certificate from the Karachi Building Control Authority (KBCA) | 51 days | no charge |
| * Takes place simultaneously with another procedure. | |||