Dealing with Construction Permits in Bulgaria

The table below summarizes the procedures, time, and costs to build a warehouse in Bulgaria.

Export to Excel | Local partners | Methodology

   View all indicator data and topic details for this economy.

Change Selection

Building a warehouse

Data as of: January 2009
Estimated Warehouse Value: BGN 780,000
City: Sofia

Requirements Summary:


  Procedure Time to complete: Cost to complete:
1 Apply and obtain the designing visa from the chief architect of the municipality 3 days BGN 300
*2 Sign preliminary contracts with the water authorities to connect to the water supply networks and obtain this connection 20 days BGN 162
*3 On-site inspection from water authorities 1 day no charge
*4 Obtain approval of visa by the Electricity provider 30 days BGN 205
5 Receive on-site inspection from Electricity provider 1 day BGN 86
6 Obtain preliminary survey from Telecom provider 15 days no charge
7 Apply for the approval for the investment design with the Chief Architect of the Municipality 30 days BGN 260
*8 Request and obtain preliminary assessment of the building for its compliance with energy efficiency requirements from licensed company 2 days BGN 1,301
*9 Obtain approval of the Investment project design from the Fire department 30 days BGN 450
*10 Obtain an expert opinion on environmental impact assessment from the Director of the Regional Inspection for the protection of the environment 30 days BGN 50
*11 Obtain approval of the Investment project design from a Hygiene Epidemiological Expert 25 days BGN 70
*12 Request the chief architect of the municipality to issue the Permission for Construction 7 days BGN 11,705
13 Sign a contract with a surveillance company 5 days BGN 10,405
14 Map the building on the cadastre 1 day BGN 30
*15 Sign contract with electricity company and receive connection 30 days BGN 9,600
*16 Sign contract with water provider and receive connection 10 days BGN 500
*17 Sign contract with telephone provider and receive connection 10 days BGN 84
18 Obtain Fire Safety certificate 1 day BGN 900
19 The construction surveillance files a report on the completed construction 1 day no charge
20 A technical passport is registered with the Chief Architect of the Municipality 3 days no charge
21 A copy of the registered technical passport is filed with the Cadastre Agency 1 day BGN 2
22 Request and obtain certificate for energy efficiency 7 days no charge
23 Receive inspection by the municipality 1 day no charge
24 The municipality issues the approval of the building 7 days BGN 750
* Takes place simultaneously with another procedure.

Requirement Details

Procedure 1.
Apply and obtain the designing visa from the chief architect of the municipality
Time to complete:
3 days
Cost to complete:
BGN 300
Name of Agency:
Municipality
Comment:
To obtain the design permit, BuildCo must submit an application form, a title of property or proof of ownership, a sketch of the acting regulation plan, and a change proposal with tax receipts. The time limit for obtaining the design permit is 14 days, according to the Law of the Spatial Planning (Article 140). The design permit fees are set according to Decision No 894, Protocol No 93 (dated November 23, 2006) of the Sofia Municipal Council, Addendum 4, Article 2, as shown below.
Fee schedule for design permit request:
- Residential buildings: BGN 40.
- Nonresidential buildings: BGN 150.

As of January 2009, the design visa can be obtained in fast track option. For nonresidential buildings it will cost BGN 300.

The documents required for issuance of a designing visa are: an application form, a title of ownership and a tax receipt.
Procedure 2.
Sign preliminary contracts with the water authorities to connect to the water supply networks and obtain this connection
Time to complete:
20 days
Cost to complete:
BGN 162
Name of Agency:
Water Authorities
Comment:
In principle, BuildCo must obtain approval from the water authorities. The approval is valid for a year. Several documents are necessary to obtain this approval, including proof of ownership, the plan, the application form, the design permit, and the investment design by the municipal?s chief architect. Because this procedure is carried out simultaneously with Procedure 2, the filing is submitted at the same time. On these grounds, the water company undertakes a preliminary survey and subsequently issues a report that contains the necessary technical data and the specifications for the network connection.

As of January 2009 the Water Company operating on the territory of Sofia has a new pricelist for the services provided. The fee amounting at BGN 162 is payable in regard with the issuance of a report containing the technical data and specifications of the water network connection. The expedited procedure is not effective anymore. It takes on average 20 days to complete this procedure.
Procedure 3.
On-site inspection from water authorities
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Water Authorities
Comment:
Procedure 4.
Obtain approval of visa by the Electricity provider
Time to complete:
30 days
Cost to complete:
BGN 205
Name of Agency:
Natsionalna Elektricheska Kompania (NEK)
Comment:
Several documents are necessary to obtain this approval, including the request form, a copy of the title document, and the design visa obtained in Procedure 2. Electricity provider experts could provide BuildCo with investment-design project consulting services, at the following rates:
- Up to 1 hour: 8.22 BGN.
- Up to 2 hours: 16.40 BGN.

A required document to obtain the municipality’s chief architect’s approval of the investment design is a preliminary contract with the electricity provider.
Procedure 5.
Receive on-site inspection from Electricity provider
Time to complete:
1 day
Cost to complete:
BGN 86
Name of Agency:
Natsionalna Elektricheska Kompania (NEK)
Comment:
Procedure 6.
Obtain preliminary survey from Telecom provider
Time to complete:
15 days
Cost to complete:
no charge
Name of Agency:
Bulgaria Telecom (BTC)
Comment:
Procedure 7.
Apply for the approval for the investment design with the Chief Architect of the Municipality
Time to complete:
30 days
Cost to complete:
BGN 260
Name of Agency:
Municipality
Comment:
The approval of the investment design is the basis for issuing a construction permit.

As of January 2009, after amendment of the Decision No 894, the fees for the approval of the investment design are BGN 0.20 per sq. m.. for the nonresidential buildings.

The procedure for the construction permit may be completed at the same time and within 7 days if the investment designs are grounds for issuing permission for construction. A respective request must be included in the application for coordination. However, many opt for separate procedures.
Procedure 8.
Request and obtain preliminary assessment of the building for its compliance with energy efficiency requirements from licensed company
Time to complete:
2 days
Cost to complete:
BGN 1,301
Name of Agency:
Licensed Company
Comment:
Every investment project for construction, reconstruction and modernization, on the basis of which permission for construction is granted, has to be assessed for its compliance with the energy efficiency requirements. The assessment is made by a company licensed thereto. There is no a fixed price for the issuance of a certificate for energy effectiveness. The rates are subject of negotiation and vary between BGN 1 - BGN 1.5 sq. m.. The assessment is done by a privately licensed company.
Procedure 9.
Obtain approval of the Investment project design from the Fire department
Time to complete:
30 days
Cost to complete:
BGN 450
Name of Agency:
Fire Department
Comment:
The fee for this procedure is equal to 50% of the cost of the certificate for fire safety issued after the completion of the construction. The latter depends on the construction category that the fire department has classified the warehouse. As of the Law of the Ministry of Interior (title amend.) SG 86/00: as of Article 31, Point 3a, Tariff No. 4), the fee formula for warehouses, industrial buildings and premises, and external facilities classified as a fire hazard "A" and "B" is BGN 250 plus BGN 0.50 per sq. m. As of 4 May 2007 fire safety procedures have been streamlined by an Order “On Conduction Fire Safety Measures”. The Order does not stipulate any new requirements regarding the construction process. However, the Order explicitly enumerates the attachments that have to be submitted together with the application in order to obtain a Certificate for Fire Safety. The validity of Certificate has been extended to 3 years. The procedure must be completed within 14 days. However in practice it still takes on average one month.
Procedure 10.
Obtain an expert opinion on environmental impact assessment from the Director of the Regional Inspection for the protection of the environment
Time to complete:
30 days
Cost to complete:
BGN 50
Name of Agency:
Regional Inspection for the Protection of the Environment
Comment:
The Law on Environment Protection (Appendix 1 and Appendix 2) defines the investment projects subject to an environmental impact assessment. The warehouse building for storing books and stationary does not fall among the investment projects listed in both appendices. Thus, the issuance of such decision is not obligatory. However, an expert opinion adopted by the competent body (e.g., the Director of the Regional Inspectorate of Protection of Environment) is required to confirm that such decision is not necessary. The expert opinion is issued within 14 days of submitting the request form and paying BGN 50 The decision is valid for 5 years.
Procedure 11.
Obtain approval of the Investment project design from a Hygiene Epidemiological Expert
Time to complete:
25 days
Cost to complete:
BGN 70
Name of Agency:
Hygiene Epidemiological Expert
Comment:
Required documents for the issuance of a hygiene certificate are a request form, a permit for designing, approval letters from water and electricity authority, expert opinion from the regional sanitary inspector, and other project documents. The hygiene epidemiological expert’s fees for consulting services are BGN 4.5 an hour. The overall cost of the approval is based on two criteria the number of experts involved in the inspection and billable hours.
Procedure 12.
Request the chief architect of the municipality to issue the Permission for Construction
Time to complete:
7 days
Cost to complete:
BGN 11,705
Name of Agency:
Municipality
Comment:
After the investment design has been approved, the permission for construction is issued within 7 days of the formal application being received. Both steps could be performed simultaneously if required in the application. The fees are BGN 9 per sq. m., according to Decision No 894, Protocol No. 93 (dated November 23, 2006, and amended in February 5, 2008) of the Sofia Municipal Council, Addendum 4, Table 1, assuming suburban Zone V.
Procedure 13.
Sign a contract with a surveillance company
Time to complete:
5 days
Cost to complete:
BGN 10,405
Name of Agency:
Surveillance Company
Comment:
BuildCo should sign a contract with an independent construction supervision firm. This supervisor must be licensed by the Ministry of Regional Development and Public Works. The supervisor will sign all acts and records during construction. The firm’s instructions and orders are binding for BuildCo and the technical manager. Within 3 days of being issued, objections against supervisory firm’s instructions can be made before the Directorate for National Construction Control. Construction will be stopped until a decision is reached, and the decision is considered to be a new set of binding rules. The supervisor must notify the Regional Directorate For National Construction control of any irregularities within 3 days of detection. The supervisor will be responsible for damages caused to the assignor and to the other participants in the construction, and jointly responsible with BuildCo for damages caused by not complying with the technical rules and the approved designs. The supervision contract must be valid for the entire construction process. The rates for a contract are between BGN 6 and BGN 10 per sq. m. of built area. However, the cost for this procedure is subject to negotiation between the investor and the surveillance company. There is no legally regulated minimum cost, but the Bulgarian Association of Architects and Engineers has issued an act containing recommended fees. The fees depend on the value of the construction work but may not be less than BGN 800. After the end of the construction, the person exercising construction supervision will prepare a final report to the assignor.
Procedure 14.
Map the building on the cadastre
Time to complete:
1 day
Cost to complete:
BGN 30
Name of Agency:
Agency for Geodesy, Cartography and Cadastre
Comment:
The Cadastre Agency issues a document after the building has been mapped. As of June 2007 the procedure can be done in fast track option in 4 hours for BGN 30. The fee is collected in the system of the Ministry of Regional Development and Public Works, according to Article 42, Paragraph 1, of the Tariff 14 promulgated SG No.94/1998. As of 03.2006 the Agency authorized to map the building on the cadastre is under the name of Agency for Geodesy, Cartography and Cadastre. The amendment is made by § 7, item 1 of the Law of the Geodesy and Cartography.
Procedure 15.
Sign contract with electricity company and receive connection
Time to complete:
30 days
Cost to complete:
BGN 9,600
Name of Agency:
Natsionalna Elektricheska Kompania (NEK)
Comment:
The fee is BGN 9,600 for connection to utility networks with a length up to 25 meters.
Procedure 16.
Sign contract with water provider and receive connection
Time to complete:
10 days
Cost to complete:
BGN 500
Name of Agency:
Water Authorities
Comment:
The decision is valid for 3 years, according to the order of the environmental protection law.
Procedure 17.
Sign contract with telephone provider and receive connection
Time to complete:
10 days
Cost to complete:
BGN 84
Name of Agency:
Bulgaria Telecom (BTC)
Comment:
Procedure 18.
Obtain Fire Safety certificate
Time to complete:
1 day
Cost to complete:
BGN 900
Name of Agency:
Fire Department
Comment:
The fee for issuing fire certificates for buildings and premises with industrial purpose, warehouses, and external facilities with fire hazard category "A" and "B" is BGN 250 plus BGN 0.50 per sq. m. This fee is set according to Tariff No. 4 for the Charges Collected Within the System of the Interior Ministry, Under the Law of the State Fees, Article 3a (amend. – SG 21/07).
Procedure 19.
The construction surveillance files a report on the completed construction
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Construction Surveillance
Comment:
After the construction is finished, the assignor, the designer, the constructor, and the supervisor, must issue a document confirming that the construction has been carried out in accordance with the approved designs, the certified executive documentation, the requirements of the construction and the conditions of the contract. The records for conducted trials on the machines and on the facilities should also be attached. The transfer of the construction by the constructor to the assignor is also implemented.
Procedure 20.
A technical passport is registered with the Chief Architect of the Municipality
Time to complete:
3 days
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The Law on Spatial Development was supplemented on September 15, 2006, State Gazette, Issue No. 76. The law contains a new requirement for licensed experts performing surveillance control. A technical passport for the construction should be prepared after the completion of construction. This document defines all terms for the performance of any major or current repairs and contains data on all certificates issued (those required by the construction legislation). Inspections should also be recorded in the passport. The technical passport must be prepared by the surveillance company. Either the surveillance company or the investor files two copies of the technical passport (one for the investor and one for the chief architect of the municipality) and an electronic copy with the Chief Architect of the Municipality, Office for Registration. The registration of the technical passport may take 2 or 3 days (no charge) after which the investor or the surveillance company may take back their original (it should bear a stamp with the date and the registration number).
Procedure 21.
A copy of the registered technical passport is filed with the Cadastre Agency
Time to complete:
1 day
Cost to complete:
BGN 2
Name of Agency:
Cadastre
Comment:
A copy of the registered original technical passport (notarization not required), along with the original technical passport, should be filed with the Cadastre Agency (this second procedure costs BGN 2 and is completed in a day). The copy is to be kept by the Cadastre Agency, while the original (with a stamped registration number) is returned to the investor.
Procedure 22.
Request and obtain certificate for energy efficiency
Time to complete:
7 days
Cost to complete:
no charge
Name of Agency:
Licensed Company
Comment:
After completing a new construction a certificate for energy efficiency (energy passport ) has to be issued, which is a part of the technical passport of the construction. The issuance of the certificate is performed under a contract signed by the assignor and natural person / entity, entered in the Register for the persons authorized to perform certification for energy efficiency.
Procedure 23.
Receive inspection by the municipality
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
National Construction Control Department
Comment:
A state commission coordinated by national Construction Control Department grants final approval of the building construction. The commission is comprised of members from different authorities, including the Hygienic Epidemiological Institute and the Fire Alarm Security Service.
Procedure 24.
The municipality issues the approval of the building
Time to complete:
7 days
Cost to complete:
BGN 750
Name of Agency:
Municipality
Comment:
After finishing the construction and tests of facilities, to obtain an occupancy permit, the assignor must register before the Chief Architect of the Municipality, present the ultimate report, the utility provider contracts, and document from the cadastral agency that its requirement has been fulfilled. In 7 days, the municipality issues the occupancy permit.