Dealing with Construction Permits in Chad
The table below summarizes the procedures, time, and costs to build a warehouse in Chad.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Chad.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Deposit technical file at municipality to apply for building permit | 90 days | XAF 2,000,000 |
| *2 | Receive inspection by telecom company SOTEL | 1 day | no charge |
| *3 | Receive inspection by cadastral services | 1 day | no charge |
| *4 | Receive technical inspection | 1 day | no charge |
| *5 | Receive inspection of water and electricity networks | 1 day | no charge |
| 6 | Obtain certificate of conformity from the Cadastre | 1 day | no charge |
| 7 | Obtain water connection | 90 days | XAF 70,000 |
| *8 | Obtain electricity connection | 60 days | XAF 600,000 |
| *9 | Obtain telephone line | 14 days | no charge |
| * Takes place simultaneously with another procedure. | |||