Building a warehouse

Data as of: January 2009
Estimated Warehouse Value: DZD 52,024,000
City: Algiers

Requirements Summary:


  Procedure Time to complete: Cost to complete:
1 Legalize property act 2 days DZD 1,800
2 Obtain building permit 150 days DZD 2,500
3 Receive municipal inspection 5 days no charge
4 Receive municipal inspection 1 day no charge
5 Receive municipal inspection 1 day no charge
6 Receive municipal inspection 1 day no charge
7 Receive municipal inspection 1 day no charge
8 Receive municipal inspection 1 day no charge
9 Request and receive final inspection to obtain certificate of conformity 14 days no charge
10 Obtain certificate of conformity 1 day DZD 5,000
11 Notarize the updated property act 1 day no charge
12 Register the updated property act (title) at the property registry 1 day no charge
13 Apply for telephone line 1 day no charge
14 Ministry of Posts and Telecommunications inspects the site and prepares an estimate 30 days DZD 13,200
15 Obtain telephone connection 30 days DZD 15,000
*16 Notify municipal/ communal authority of connection to sewer mains 1 day no charge
17 Apply for electricity connection 1 day DZD 25,000
18 Electricity company inspects the site and prepares an estimate 14 days DZD 15,000
19 Obtain electricity connection 25 days DZD 12,500
20 Apply for water connection 1 day no charge
21 The water company inspects the site and prepares an estimate 22 days DZD 13,000
22 Obtain water connection 18 days DZD 25,000
* Takes place simultaneously with another procedure.

Requirement Details

Procedure 1.
Legalize property act
Time to complete:
2 days
Cost to complete:
DZD 1,800
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 2.
Obtain building permit
Time to complete:
150 days
Cost to complete:
DZD 2,500
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 3.
Receive municipal inspection
Time to complete:
5 days
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 4.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
The law does not specify the number of inspections that take place during construction. However, inspections occur randomly before and during the construction process. The variation depends on the visibility and on the exact location of the construction site.
Procedure 5.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 6.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 7.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 8.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 9.
Request and receive final inspection to obtain certificate of conformity
Time to complete:
14 days
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
When the warehouse is completed, BuildCo must notify the municipality so that it can perform a final inspection of the construction. The inspector will usually arrive on site within 2 weeks of the request.
Procedure 10.
Obtain certificate of conformity
Time to complete:
1 day
Cost to complete:
DZD 5,000
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Although the law requires a certificate of conformity, it is seldom issued in practice.
Procedure 11.
Notarize the updated property act
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 12.
Register the updated property act (title) at the property registry
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Before the building can be used as collateral, banks require the property title and the construction license. This case study assumes that BuildCo possesses a construction license.

Procedure 13.
Apply for telephone line
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:


Procedure 14.
Ministry of Posts and Telecommunications inspects the site and prepares an estimate
Time to complete:
30 days
Cost to complete:
DZD 13,200
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:
The Ministry of Posts and Telecommunications requires a 50% down payment on the estimated charge before connecting the building.
Procedure 15.
Obtain telephone connection
Time to complete:
30 days
Cost to complete:
DZD 15,000
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:
A site visit may be required to prepare the estimate.
Procedure 16.
Notify municipal/ communal authority of connection to sewer mains
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal/communal authority (Autorité municipale/communale)
Comment:
Procedure 17.
Apply for electricity connection
Time to complete:
1 day
Cost to complete:
DZD 25,000
Name of Agency:
Socièté Nationale de l'Electricité et du Gaz (SONELGAZ)
Comment:
Procedure 18.
Electricity company inspects the site and prepares an estimate
Time to complete:
14 days
Cost to complete:
DZD 15,000
Name of Agency:
Socièté Nationale de l'Electricité et du Gaz (SONELGAZ)
Comment:
A site visit is sometimes required to prepare the estimate.
Procedure 19.
Obtain electricity connection
Time to complete:
25 days
Cost to complete:
DZD 12,500
Name of Agency:
Socièté Nationale de l'Electricité et du Gaz (SONELGAZ)
Comment:
Procedure 20.
Apply for water connection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
SEAAL
Comment:
Procedure 21.
The water company inspects the site and prepares an estimate
Time to complete:
22 days
Cost to complete:
DZD 13,000
Name of Agency:
SEAAL
Comment:
A site visit is sometimes required to prepare the estimate.



Procedure 22.
Obtain water connection
Time to complete:
18 days
Cost to complete:
DZD 25,000
Name of Agency:
SEAAL
Comment: