Procedure 1.
Legalize property act
Time to complete:
2 days
Cost to complete:
DZD 1,800
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 2.
Obtain building permit
Time to complete:
150 days
Cost to complete:
DZD 2,500
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 3.
Receive municipal inspection
Time to complete:
5 days
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 4.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
The law does not specify the number of inspections that take place during construction. However, inspections occur randomly before and during the construction process. The variation depends on the visibility and on the exact location of the construction site.
Procedure 5.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 6.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 7.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 8.
Receive municipal inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 9.
Request and receive final inspection to obtain certificate of conformity
Time to complete:
14 days
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
When the warehouse is completed, BuildCo must notify the municipality so that it can perform a final inspection of the construction. The inspector will usually arrive on site within 2 weeks of the request.
Procedure 10.
Obtain certificate of conformity
Time to complete:
1 day
Cost to complete:
DZD 5,000
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Although the law requires a certificate of conformity, it is seldom issued in practice.
Procedure 11.
Notarize the updated property act
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Procedure 12.
Register the updated property act (title) at the property registry
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipal authority (Autorité municipale)
Comment:
Before the building can be used as collateral, banks require the property title and the construction license. This case study assumes that BuildCo possesses a construction license.
Procedure 13.
Apply for telephone line
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:
Procedure 14.
Ministry of Posts and Telecommunications inspects the site and prepares an estimate
Time to complete:
30 days
Cost to complete:
DZD 13,200
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:
The Ministry of Posts and Telecommunications requires a 50% down payment on the estimated charge before connecting the building.
Procedure 15.
Obtain telephone connection
Time to complete:
30 days
Cost to complete:
DZD 15,000
Name of Agency:
Ministry of Posts and Telecommunications (Ministère des Postes et Télécommunications)
Comment:
A site visit may be required to prepare the estimate.
Procedure 16.
Notify municipal/ communal authority of connection to sewer mains