The table below summarizes the procedures, time, and costs to build a warehouse in Congo, Rep..

Export to Excel | Local partners | Methodology

   View all indicator data and topic details for this economy.

Change Selection

Building a warehouse

Data as of: January 2009
Estimated Warehouse Value: XAF 390,180,000
City: Brazzaville

Requirement Details

Procedure 1.
Obtain survey map
Time to complete:
3 days
Cost to complete:
XAF 10,000
Name of Agency:
Survey Department (Direction des Cadastres)
Comment:
The cost includes XAF 5,000 for the documents, XAF 2,000 for reproduction, and XAF 3,000 for labor.
Procedure 2.
Obtain building permit
Time to complete:
2 days
Cost to complete:
no charge
Name of Agency:
Mayor’s Office, Brazzaville
Comment:
The required documents to obtain a building permit are the following - Occupation permit or land title. - Survey abstract. - Very large-scale boundary plan, drawn up by the Lands and Survey Department (Direction du Cadastre et de la Topographie). - Sketches and drawings of the proposed works, produced by an architect or a certified draftsman. - Building permit application (handwritten). - Authorization for the cutting and clearing of trees, if necessary. - Certification of party walls (walls shared by tenants of adjoining buildings). - A certified undertaking to build and maintain streets adjoining the elevations.
Procedure 3.
Obtain review by the General Directorate for Construction and Urban Planning (Direction Générale de Construction et de l’urbanisme) and pay fees
Time to complete:
35 days
Cost to complete:
XAF 30,000
Name of Agency:
General Directorate for Construction and Urban Planning (Direction Générale de Construction et de l’urbanisme)
Comment:
Procedure 4.
Obtain a building permit
Time to complete:
50 days
Cost to complete:
XAF 450,000
Name of Agency:
Mayor’s Office, Brazzaville
Comment:
The building permit is obtained after notifying the cadastre and curator (conservateur).
Procedure 5.
Contract a private building inspection company
Time to complete:
1 day
Cost to complete:
USD 3,902
Name of Agency:
Private inspection company
Comment:
The Doing Business project assumes the cost of construction to be about USD 300 per square meter. The fees for one private inspection may vary between 0.5% and 5% of the cost of the construction, but a project of this size will be about 1% of construction.
Procedure 6.
Apply for connection to water mains
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Société Nationale de Distribution d'Eau
Comment:
Procedure 7.
Receive inspection for purposes of drawing up the estimate
Time to complete:
7 days
Cost to complete:
no charge
Name of Agency:
Société Nationale de Distribution d'Eau
Comment:
A cost estimate (devis) is needed for both electricity and water.
Procedure 8.
Connection to water mains
Time to complete:
70 days
Cost to complete:
XAF 58,200
Name of Agency:
Société Nationale de Distribution d'Eau
Comment:
Procedure 9.
Apply for connection to the electricity mains
Time to complete:
1 day
Cost to complete:
XAF 7,000
Name of Agency:
Société Nationale d'Electricité (SNE)
Comment:
Procedure 10.
Receive inspection for purposes of drawing up the estimate
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Société Nationale d'Electricité (SNE)
Comment:
The contractor may pay XAF 10,000 to cover transport expenses incurred by the building inspectors.
Procedure 11.
Connect to electricity mains
Time to complete:
20 days
Cost to complete:
XAF 60,436
Name of Agency:
Société Nationale d'Electricité (SNE)
Comment:
The fee for electrical connection is XAF 60,436 for aerial connection or XAF 67,273 for underground connection.
Procedure 12.
Apply for a telephone line
Time to complete:
1 day
Cost to complete:
XAF 4,165
Name of Agency:
Congo Telecom & Communication
Comment:
Procedure 13.
Receive inspection for purposes of drawing up the estimate
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Congo Telecom & Communication
Comment:
Procedure 14.
Obtain installation of telephone line
Time to complete:
35 days
Cost to complete:
XAF 83,230
Name of Agency:
Congo Telecom & Communication
Comment: