Dealing with Construction Permits in Dominica
The table below summarizes the procedures, time, and costs to build a warehouse in Dominica.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Dominica.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| *1 | Obtain Outline Planning Permission | 56 days | XCD 50 |
| 2 | Obtain Planning permission | 90 days | XCD 1,000 |
| 3 | Request and receive inspection of building setout with approved setbacks | 1 day | no charge |
| 4 | Request and receive inspection of substructure (foundation) | 1 day | no charge |
| 5 | Request and receive inspection of framing for roof | 1 day | no charge |
| 6 | Request and obtain electrical certificate | 14 days | XCD 15 |
| 7 | Request for electricity connection | 1 day | no charge |
| 8 | Receive electricity inspection | 1 day | no charge |
| 9 | Obtain electricity connection | 14 days | no charge |
| *10 | Request for water-sewage connection | 1 day | no charge |
| *11 | Receive water - sewage inspection | 1 day | no charge |
| *12 | Obtain water - sewage connection | 14 days | XCD 240 |
| *13 | Obtain a fixed telephone line | 3 days | XCD 150 |
| * Takes place simultaneously with another procedure. | |||