Dealing with Construction Permits in Dominica

The table below summarizes the procedures, time, and costs to build a warehouse in Dominica.

Export to Excel | Local partners | Methodology

   View all indicator data and topic details for this economy.

Change Selection

Building a warehouse

Data as of: January 2009
Estimated Warehouse Value: XCD 240,611
City: Roseau

Requirements Summary:


  Procedure Time to complete: Cost to complete:
*1 Obtain Outline Planning Permission 56 days XCD 50
2 Obtain Planning permission 90 days XCD 1,000
3 Request and receive inspection of building setout with approved setbacks 1 day no charge
4 Request and receive inspection of substructure (foundation) 1 day no charge
5 Request and receive inspection of framing for roof 1 day no charge
6 Request and obtain electrical certificate 14 days XCD 15
7 Request for electricity connection 1 day no charge
8 Receive electricity inspection 1 day no charge
9 Obtain electricity connection 14 days no charge
*10 Request for water-sewage connection 1 day no charge
*11 Receive water - sewage inspection 1 day no charge
*12 Obtain water - sewage connection 14 days XCD 240
*13 Obtain a fixed telephone line 3 days XCD 150
* Takes place simultaneously with another procedure.

Requirement Details

Procedure 1.
Obtain Outline Planning Permission
Time to complete:
56 days
Cost to complete:
XCD 50
Name of Agency:
Development and Planning Corporation (D & PC)
Comment:
Procedure 2.
Obtain Planning permission
Time to complete:
90 days
Cost to complete:
XCD 1,000
Name of Agency:
Development and Planning Corporation (D & PC)
Comment:
Procedure 3.
Request and receive inspection of building setout with approved setbacks
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Development and Planning Corporation (D & PC)
Comment:
According to the building code, nine inspections should be conducted during the construction process. Each inspection occurs within 48 hours of being requested by the contractor for review. However, only three occur in practice. There are no fees for the inspections.
Procedure 4.
Request and receive inspection of substructure (foundation)
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Development and Planning Corporation (D & PC)
Comment:
Procedure 5.
Request and receive inspection of framing for roof
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Development and Planning Corporation (D & PC)
Comment:
Procedure 6.
Request and obtain electrical certificate
Time to complete:
14 days
Cost to complete:
XCD 15
Name of Agency:
Electrical Division
Comment:
Procedure 7.
Request for electricity connection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Dominica Electricity Service Ltd. (DOMLEC)
Comment:
Procedure 8.
Receive electricity inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Dominica Electricity Service Ltd. (DOMLEC)
Comment:
The inspection is conducted by the electrical division of the Development and Planning Corporation. If the building passes inspection, it receives a certificate permitting the electricity installation.
Procedure 9.
Obtain electricity connection
Time to complete:
14 days
Cost to complete:
no charge
Name of Agency:
Dominica Electricity Service Ltd. (DOMLEC)
Comment:
To obtain an electricity connection, BuildCo must comply with official requirements that require the customer to provide load requirements, voltage(s), and watts; submit a certification of installation from the government’s electrical division; and pay a contribution toward the power supply connection. Where a line extension is required, the customer must give the company much advance notice.
Procedure 10.
Request for water-sewage connection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Dominica Water and Sewage Company (DOWASCO)
Comment:
Procedure 11.
Receive water - sewage inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Dominica Water and Sewage Company (DOWASCO)
Comment:
Procedure 12.
Obtain water - sewage connection
Time to complete:
14 days
Cost to complete:
XCD 240
Name of Agency:
Dominica Water and Sewage Company (DOWASCO)
Comment:
Procedure 13.
Obtain a fixed telephone line
Time to complete:
3 days
Cost to complete:
XCD 150
Name of Agency:
Cable and Wireless
Comment: