provides objective measures of business regulations and their enforcement across 183 economies and selected cities at the subnational and regional level. Learn more...
* Takes place simultaneously with another procedure.
Requirement Details
Procedure 1.
Obtain technical approvals from independent syndicate engineer
Time to complete:
9 days
Cost to complete:
EGP 1,750
Name of Agency:
Independent syndicate engineer
Comment:
To obtain technical approvals, BuildCo must submit documents, including the approval of the colored cadastral map; the approval of probe estimation; the execution supervision certificate (fee EGP 250–350); approval of architectural drawings (fee EGP 150–200); accounting book; report confirming the construction quality of the building foundations (fee EGP 250–300); and a soil investigation report (fee EGP 1,000).
Procedure 2.
Submit building permit application to municipal authority
Time to complete:
1 day
Cost to complete:
EGP 7
Name of Agency:
Municipality
Comment:
To obtain a building permit, BuildCo must file with the District Department the following documents, along with the ones described in the previous procedures: - Original ownership contract of the plot of land (notarized). - Measurement specification statement from the Survey Department. - Survey plan (aerial photography) specifying the location. That survey plan must be approved by an accredited syndicate engineer. - Alignment license, issued by the Urban Planning Department of Cairo Governorate. - Probe estimation, approved by a syndicated engineer - Execution supervision certificate, issued by a syndicate engineer or consultant engineer, if the building value is more than EGP 1 million. - A receipt attesting the payment of fees for the duty for examination of the drawings and details - A general drawing of the site (scale minimum 1:1,000) that indicates (a) the boundaries and dimensions of the land for which the permit is required, together with the total land area; and (b) the part on which construction is requested, as well as the facing roads and their widths. BuildCo must submit a file containing (a) a copy of the architectural drawings for the horizontal projections of floors and facades; (b) a vertical section, indicating the building height and the road's zero level and the structural drawings of the foundations, columns, and the enforced ceilings, together with copies of the structural calculation notes. All drawings must be signed by an accredited engineer. Also to be filed is a report from a structural engineer that confirms the structural skeleton and the foundations of the building (a) will tolerate the required licensed construction work and (b) are in compliance with safety provisions and will resist natural disasters according to Egyptian construction standards. The report must illustrate the soil composition at the site. If the building is elevated or modified, BuildCo must submit a report from a construction consultant (accredited for not less than 25 years), attesting that upon inspection and study of the existing buildings, the consultant has obtained proof of tolerance to the applicable loads subject to the license.
Procedure 3.
Obtain project clearance from electricity authority
Time to complete:
30 days
Cost to complete:
no charge
Name of Agency:
Greater Cairo Electricity Authority
Comment:
Procedure 4.
Receive inspection prior to permit issuance from muncipality
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
Procedure 5.
Pay real estate tax at the tax authority
Time to complete:
1 day
Cost to complete:
EGP 30
Name of Agency:
Tax Authority
Comment:
Procedure 6.
Obtain building permit
Time to complete:
30 days
Cost to complete:
EGP 2,000
Name of Agency:
Municipality
Comment:
The Construction Law establishes a 30-day statutory time limit for issuing building permits. These 30 days are counted only after all preliminary approvals are obtained. Law 4 of 2006 reduced the fee to obtain a building permit from 1% of construction cost to 0.2%.
Procedure 7.
Receive on-site inspection from the municipality - I
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 8.
Receive on-site inspection from the municipality - II
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 9.
Receive on-site inspection from the municipality - III
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 10.
Receive on-site inspection from the municipality - IV
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 11.
Receive on-site inspection from the municipality - V
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 12.
Receive on-site inspection from the municipality - VI
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 13.
Receive on-site inspection from the municipality - VII
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 14.
Receive on-site inspection from the municipality - VIII
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 15.
Receive on-site inspection from the municipality - IX\
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 16.
Receive on-site inspection from the municipality - X
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
The municipality will inspect the construction site on a regular basis (usually once a month but inspections can occur once every 2 weeks). Each inspection takes a day at most. It is assumed that the site is inspected every 3 weeks on average.
Procedure 17.
Receive final inspection from by a committee from the Municipal Authority
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Municipality
Comment:
After construction is done, the municipality makes a final inspection to certify that the warehouse conforms to the specifications outlined in the building permit.
Procedure 18.
Obtain letters from Municipality about water and sewage connection and about electricity cables installation
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Greater Cairo Water Authority
Comment:
As described above, the company must obtain a form from the municipality to obtain water and sewage connections.
Procedure 19.
Obtain certificate of natural disaster
Time to complete:
1 day
Cost to complete:
EGP 102
Name of Agency:
Independent Syndicate Engineer
Comment:
A supervising engineer issues the certificate of natural disaster. The cost cited here reflects the fees for issuing the certificate.
Procedure 20.
Obtain water and sewerage connection
Time to complete:
60 days
Cost to complete:
EGP 15,000
Name of Agency:
Greater Cairo Water Authority
Comment:
BuildCo submits an application to the municipal department to obtain a letter to be provided to the water utility. Then the company submits an application to the competent water authority, along with the original license and a copy of the building permit. Fees include about EPG 10,000 for the water connection and EPG 5,000 for the sewerage connection.
Procedure 21.
Apply for electricity connection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Greater Cairo Electricity Authority
Comment:
For the electricity authority to extend the electric cables network, the company must submit the electrical design drawings to be endorsed by the authority and electricity company.
Procedure 22.
Receive electricity inspection
Time to complete:
1 day
Cost to complete:
no charge
Name of Agency:
Greater Cairo Electricity Authority
Comment:
The electricity authority inspects the construction site to provide a cost estimate.
Procedure 23.
Obtain electricity connection
Time to complete:
19 days
Cost to complete:
EGP 15,000
Name of Agency:
Greater Cairo Electricity Authority
Comment:
Connection fees include laying down the cables.
Procedure 24.
Obtain phone connection
Time to complete:
18 days
Cost to complete:
EGP 850
Name of Agency:
Telecom Egypt
Comment:
To obtain a phone connection, the company must submit the following documents: - Title deed for the unit, or lease contract, if not owned by the applicant. - Copy of applicant’s identification. - Operators license for factories, stores, commercial stores, and workshops.
Procedure 25.
Register the building with the real estate registry
Time to complete:
75 days
Cost to complete:
EGP 2,000
Name of Agency:
Real Estate Registry
Comment:
The company must submit a building registration form, the building permit for the warehouse, and the primary purchase contract of the land on which the warehouse had been built. Law 83 of 2006 amended Decree No. 70 (1964) to decrease registration fees, which are now a flat fee of EGP 2,000 rather than a percentage of building value.