Dealing with Construction Permits in Estonia
The table below summarizes the procedures, time, and costs to build a warehouse in Estonia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Estonia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain design criteria from Municipal authority | 15 days | no charge |
| 2 | Obtain project clearance from fire department | 30 days | no charge |
| *3 | Submit Environmental Impact Assessment | 7 days | no charge |
| *4 | Obtain project clearance from Environment Department | 29 days | no charge |
| *5 | Obtain project clearance from health care department | 28 days | no charge |
| *6 | Obtain project clearance from labor inspections department | 27 days | no charge |
| 7 | Obtain building permit | 25 days | EEK 8,503 |
| 8 | Receive on-site inspection by municipal authority | 1 day | no charge |
| 9 | Receive on-site inspection by Estonian Technical Surveyllance Authority | 1 day | no charge |
| 10 | Apply for permit of use and request final inspection from municipal authority | 25 days | EEK 1,000 |
| *11 | Receive final inspection from municipal authority | 1 day | no charge |
| 12 | Obtain sewerage and water connection | 20 days | EEK 17,500 |
| 13 | Obtain electric power connection | 15 days | EEK 17,972 |
| 14 | Obtain telephone connection | 15 days | EEK 1,524 |
| * Takes place simultaneously with another procedure. | |||