Dealing with Construction Permits in Ethiopia
The table below summarizes the procedures, time, and costs to build a warehouse in Ethiopia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Ethiopia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain design approval | 60 days | ETB 10,000 |
| 2 | Obtain consent from neighbors and submit it to municipality | 3 days | no charge |
| 3 | Obtain bank statement | 1 day | no charge |
| 4 | Obtain approval of construction | 30 days | ETB 600 |
| 5 | Request and receive excavation inspection from municipality | 1 day | no charge |
| 6 | Request and receive mid-construction inspection | 1 day | no charge |
| 7 | Request electricity connection from EEPCo | 1 day | no charge |
| 8 | Receive electricity inspection from EEPCo | 1 day | no charge |
| 9 | Obtain electricity connection from EEPCo | 28 days | ETB 500 |
| *10 | Request water and sewage connection from WSSA | 1 day | no charge |
| 11 | Obtain water and sewage connection from WSSA | 29 days | ETB 4,000 |
| *12 | Obtain telephone connection from ETC | 30 days | ETB 2,000 |
| * Takes place simultaneously with another procedure. | |||