Dealing with Construction Permits in Angola
The table below summarizes the procedures, time, and costs to build a warehouse in Angola.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Angola.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain a Proof of Title of Property for the Land | 15 days | AOA 3,000 |
| 2 | Obtain permission to build from Fire department | 5 days | no charge |
| 3 | Request License to Build from the Provincial Governor | 180 days | AOA 13,200 |
| *4 | Receive on-site inspection from the Provincial Government | 1 day | no charge |
| *5 | Obtain approval from telephone provider (Angola Telecom) | 1 day | no charge |
| 6 | Hire inspection firm | 1 day | AOA 632,640 |
| 7 | Obtain occupancy permit and request inspection by provincial authorities | 30 days | AOA 2,000 |
| *8 | Receive final inspection by provincial authorities | 1 day | no charge |
| 9 | Obtain electric power connection | 16 days | AOA 1,107,134 |
| *10 | Obtain telephone connection | 15 days | AOA 7,908 |
| *11 | Obtain water and sewage connection | 10 days | no charge |
| 12 | Register the building with the real estate registry | 90 days | no charge |
| * Takes place simultaneously with another procedure. | |||