Dealing with Construction Permits in France
The table below summarizes the procedures, time, and costs to build a warehouse in France.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in France.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain building permit | 60 days | no charge |
| 2 | Declare intention to build to the prefecture | 1 day | no charge |
| 3 | Apply for water connection | 1 day | no charge |
| 4 | SEDIF visits the site to prepare a cost estimate (devis) for water connection | 1 day | no charge |
| 5 | Apply for electricity connection | 1 day | no charge |
| *6 | EDF visits the site to prepare a cost estimate (devis) for the electricity connection | 1 day | no charge |
| 7 | Approved permit is publicly displayed | 60 days | no charge |
| *8 | File a declaration of the worksite opening | 1 day | no charge |
| *9 | Declare completion of construction | 1 day | no charge |
| *10 | Receive visit by building inspectors and obtain compliance certificate | 1 day | no charge |
| 11 | Obtain electricity connection | 68 days | EUR 3,138 |
| *12 | Obtain water connection | 38 days | EUR 4,000 |
| *13 | Obtain telephone connection | 60 days | EUR 130 |
| * Takes place simultaneously with another procedure. | |||