Dealing with Construction Permits in Georgia
The table below summarizes the procedures, time, and costs to build a warehouse in Georgia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Georgia.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Request and obtain extract from the National Public Registry | 1 day | GEL 15 |
| 2 | Request and obtain Terms of Construction from Tbilisi Urban Planning Service | 30 days | no charge |
| 3 | Request and obtain building permit from Tbilisi Urban Planning Service | 10 days | GEL 650 |
| 4 | Request and receive connection to water/sewage service | 2 days | no charge |
| 5 | Request and obtain connection to electricity service | 2 days | no charge |
| 6 | Request and obtain connection to telephone services | 5 days | GEL 120 |
| 7 | Request and obtain layout survey and protocol from Archmshen Inspection (Architectural Inspection Agency) | 1 day | no charge |
| 8 | Request and obtain protocol of completion of major building structure from Archmshen Inspection | 1 day | no charge |
| 9 | Request and obtain exploitation of building- construction from Special Commission | 15 days | no charge |
| 10 | Register the building with the National Public registry | 1 day | GEL 150 |