Dealing with Construction Permits in Greece
The table below summarizes the procedures, time, and costs to build a warehouse in Greece.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Greece.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain copy of notary deed | 1 day | no charge |
| *2 | Obtain copy of land registry certificate | 1 day | no charge |
| *3 | Obtain waste disposal study | 10 days | no charge |
| *4 | Obtain active fire protection approval | 10 days | no charge |
| 5 | Obtain installation permit | 15 days | no charge |
| 6 | Obtain building permit | 90 days | no charge |
| *7 | Pay workers’ social security | 3 days | no charge |
| 8 | Obtain police approval for the commencement of works | 3 days | no charge |
| *9 | Obtain municipal approval for the commencement of works and for the occupation of pavement | 3 days | EUR 600 |
| 10 | Receive final inspection from the municipality | 1 day | no charge |
| 11 | Request and obtain electric power connection | 45 days | EUR 10,000 |
| *12 | Obtain water connection | 45 days | EUR 35 |
| *13 | Obtain sewage connection | 7 days | EUR 1 |
| *14 | Obtain telephone connection | 7 days | EUR 30 |
| 15 | Register the building with the Municipal Authorities | 1 day | no charge |
| * Takes place simultaneously with another procedure. | |||