Dealing with Construction Permits in Grenada
The table below summarizes the procedures, time, and costs to build a warehouse in Grenada.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.
The table below summarizes the procedures, time, and costs to build a warehouse in Grenada.
Export to Excel | Local partners | Methodology
View all indicator data and topic details for this economy.| Procedure | Time to complete: | Cost to complete: | |
|---|---|---|---|
| 1 | Obtain location plan from Land and Survey Office | 1 day | no charge |
| 2 | Obtain Development Permit from Land Development Control Authority | 90 days | XCD 3,000 |
| 3 | Request and receive final inspection from the Land Development Control Authority | 15 days | XCD 170 |
| 4 | Obtain Certificate of Occupancy form the Land Development Control Authority | 7 days | XCD 5 |
| 5 | Receive electricity inspection and obtain electricity inspection certificate -internal wiring | 1 day | no charge |
| 6 | Request and obtain electricity service | 35 days | XCD 350 |
| *7 | Request water service | 1 day | no charge |
| *8 | Receive water inspection | 1 day | no charge |
| *9 | Obtain Water and Sewage Connection | 7 days | XCD 120 |
| *10 | Obtain Fixed Telephone Line | 7 days | XCD 250 |
| * Takes place simultaneously with another procedure. | |||