| Time to complete: | 50 days |
| Cost to complete: | INR 10000 |
| Comment: | Land use approval from the Industrial Infrastructure Development Corporation is required if the construction is to be carried on in the Industrial area. Any area falling outside the Industrial area requires land use approval from the Revenue Department of |
| Time to complete: | 5 days |
| Cost to complete: | INR 4,000 (INR 3,175 to INR 5,000) |
| Comment: | The company must submit the application in Form 1 to the Bhubaneshwar Development Authority along with the following documents:
a) Four copies of plans duly signed by the applicant showing site plan, layout plan with roads, plan of all floors, four side e |
| Time to complete: | 52 days |
| Cost to complete: | INR 20,000 |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area.
In case |
| Time to complete: | 15 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 3500 |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | In the present case, the connection can be a LT connection. The Cost is estimated by the licensee (CESCO) by calculating the load, the number of points connection for electricity (Switches, plugs, appliances etc.) + Security amount. |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | INR 7500 |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | The time of obtaining a phone connection decreased from 2 months in to 1 week over the past couple of years. |
| Time to complete: | 30 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 28 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |