| Time to complete: | 45 days |
| Cost to complete: | INR 10000 |
| Comment: | The company must submit the application in Form A to the Estate Office along with the following documents:
a) A site plan: position of lot (in triplicate);
b) Plans, elevations, and sections (in triplicate):
c) Drainage plans, structural and electrical dr |
| Time to complete: | 1 day, simultaneous with previous procedure |
| Cost to complete: | INR 80 (INR 30 for the affidavit and INR 50 for the indemnity bond) |
| Comment: | |
| Time to complete: | 5 days |
| Cost to complete: | INR 10000 |
| Comment: | |
| Time to complete: | 37 days |
| Cost to complete: | INR 22,500 (INR 20,000- 25,000) |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. |
| Time to complete: | 28 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 26 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 28 days |
| Cost to complete: | no charge |
| Comment: | The company should inform the local authority about completion of the finishing work (white waxing, coloring, fixing, water supply, drainage, or other sanitary fitments), before obtaining regular connection for water supply/electricity. |
| Time to complete: | 30 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 3500 |
| Comment: | |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | INR 65,030 (INR 50 per square meter) |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | INR 2,500 (INR 2,000-3,000) |
| Comment: | |
| Time to complete: | 3 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Time to complete: | 45 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |