| Time to complete: | 50 days |
| Cost to complete: | INR 8000 |
| Comment: | |
| Time to complete: | 5 days |
| Cost to complete: | INR 300 |
| Comment: | The company must submit the application to Jaipur Municipal Corporation along with the following documents:
a) Five copies (two cloth mounted) of building plan;
b) Evidence like Record of Rights (ROR) or a civil court decree as regards title and possessio |
| Time to complete: | 30 days |
| Cost to complete: | INR 26000 |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. |
| Time to complete: | 35 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 33 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 20 days |
| Cost to complete: | INR 1000 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 40 days |
| Cost to complete: | INR 5500 |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Time to complete: | 45 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 25 days |
| Cost to complete: | INR 30 per square meter |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |