| Time to complete: | 60 days |
| Cost to complete: | INR 200. (administrative fee) |
| Comment: | |
| Time to complete: | 10 days |
| Cost to complete: | no charge |
| Comment: | Clearance from Directorate of Fire: If any building of more than 15 meters in height and other buildings with more than 500 sq. m ground coverage and all other buildings of industrial or storage ( as warehouse) assembly or hazardous use is to be constru |
| Time to complete: | 30 days |
| Cost to complete: | INR 210 (INR 200 per plot + INR 10 Application fee) |
| Comment: | Approval by the Authority after inspection : It has to be obtained before applying for the Building permit to the PRDA. This is done to check whether the site plan and the building plan are viable. |
| Time to complete: | 5 days |
| Cost to complete: | INR 13,500 |
| Comment: | A building permit is valid for 3 years during which period completion certificate shall be submitted .The cost includes the fee payble to the PRDA and other expenses incurred in documentation but it does not include the cost likely to be incurred in drawi |
| Time to complete: | 129 days |
| Cost to complete: | included in previous procedure |
| Comment: | see above |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | no charge |
| Comment: | After Buildco Notifies the Patna Regional Development Authority about the commencement of earth work for foundation it must receive a foundation inspection and commencement certificate from the PRDA |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 3 days |
| Cost to complete: | no charge |
| Comment: | Buildco must notify the Patna Regional Development Authority about the completion of finishing work and Receive finishing work inspection |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 3,500 |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | INR 3,200 (sewage) + INR 500 (water connection) |
| Comment: | |
| Time to complete: | 45 days |
| Cost to complete: | INR 63,000 |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | INR 1,500 + security deposit |
| Comment: | |
| Time to complete: | 40 days |
| Cost to complete: | INR 2,500 |
| Comment: | |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | no charge |
| Comment: | The PRDA issues an occupancy certificate affirming thereby that such building is fit for occupation. For the warehouse, a joint inspection by the PRDA and the Director of the Fire Services is done, before issuance of the occupancy certificate. |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |