| Time to complete: | 15 days |
| Cost to complete: | PKR 250 |
| Comment: | BuildCo must produce all title documents relating to the plot(s) which confirm the right of BuildCo to undertake construction on the plots. |
| Time to complete: | 45 days |
| Cost to complete: | PKR 10,000 |
| Comment: | BuildCo is required to submit an Environmental Impact Statement (EIS) on the prescribed form, for review and approval of the Director-General, Environment Protection Agency (EPA), NWFP, Old Court Building, Khyber Road, Peshawar.
The proforma typically inc |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 30 days |
| Cost to complete: | PKR 70,000 (PKR 5 scrutiny fee per square foot) |
| Comment: | BuildCo must submit to the Building Control Agency on the prescribed form, an application seeking permission to undertake the construction work. The application will be accompanied by four signed copies of following documents prepared by a registered arch |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 35 days |
| Cost to complete: | PKR 174,800 |
| Comment: | An application in the prescribed form shall be submitted to the local office of the Peshawar Electric Supply Company Limited (“PESCO”) along with the following documents:
(i) An attested copy of the applicant’s National Identity Card (NIC).
(ii) Attested |
| Time to complete: | 3 days |
| Cost to complete: | PKR 6,800 |
| Comment: | In case of a load in excess of 5 kw, an inspection should be conducted by a private licensed contractor, and his report must then be submitted to PESCO by the applicant. |
| Time to complete: | 10 days |
| Cost to complete: | PKR 3,050 |
| Comment: | Connection time subject to availability |
| Time to complete: | 10 days |
| Cost to complete: | PKR 6,000 |
| Comment: | BuildCo will file an application on a prescribed form addressed to Deputy Director (Water & Sanitation) of CD&MD/ TMA (Works and Services Department) for sewage connection. The following document should be appended with the application:
(i) An attested co |
| Time to complete: | 10 days |
| Cost to complete: | no charge |
| Comment: | Within thirty days of completion of construction BuildCo will file an application with the Building Control Agency of CD&MD/ TMO (W&S) for issuance of the Completion Certificate on a prescribed form. The Building Inspector will inspect the building to con |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |