| Time to complete: | 15 days |
| Cost to complete: | PKR 350 |
| Comment: | The company must obtain a letter from the concerned authority (Quetta Development Authority or the Town Municipal Administration) confirming the title/land use physically fresh demarcated/dimensions of the plot along with the existence of any road widenin |
| Time to complete: | 75 days |
| Cost to complete: | PKR 10,000 |
| Comment: | BuildCo is required to submit an Environmental Impact Statement (EIS) for review and approval by the Director-General, Environment Protection Agency, Punjab, 4-Lytton Road, Lahore.
The statement shall include the following:
1. Name & location of industria |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 15 days |
| Cost to complete: | PKR 49,000 (assuming PKR 3.5 per square feet) |
| Comment: | Preparation of Building Plans (to be approved from the TMA Quetta).
BuildCo is required to get the detail building plans prepared through a Registered Architect (duly registered with the Pakistan Council of Architects and Town Planners under the PCATP Ord |
| Time to complete: | 1 day |
| Cost to complete: | PKR 52,500 (+ PKR 35,000 refundable fee) |
| Comment: | Payment of required Fees to TMA Quetta for approval of Building Plan
The fees are paid to TMA Quetta through Challan, prepared in triplicate by TMA Official and paid into the Bank , with a two copies returned and one to be submitted to TMA for proof of p |
| Time to complete: | 53 days |
| Cost to complete: | included in previous procedure |
| Comment: |
Once all the documents are filed and necessary fee paid, the TMA Quetta initiates the scrutiny process. The Town Officer makes the necessary verification that whether the Application is in order and all the documents required under law are filed. If the |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | During construction, BuildCo will receive several surprise visits from teams of Building Control Agency of the Town Municipal Admistration to verify on spot that the construction is carried out in accordance with Plans and is not violative of any building |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | During construction, BuildCo will receive several surprise visits from teams of Building Control Agency of the Town Municipal Admistration to verify on spot that the construction is carried out in accordance with Plans and is not violative of any building |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | During construction, BuildCo will receive several surprise visits from teams of Building Control Agency of the Town Municipal Admistration to verify on spot that the construction is carried out in accordance with Plans and is not violative of any building |
| Time to complete: | 38 days |
| Cost to complete: | PKR 176,800 |
| Comment: | An application in the prescribed form will be required to be submitted to the Quetta Electricity Supply Corporation Limited along with the following documents for a new electricity connection:
(i) Certificate of Incorporation of the BuildCo.
(ii) Proo |
| Time to complete: | 3 days |
| Cost to complete: | PKR 10,000 |
| Comment: | If the required load is above 5kW, there must be an inspection conducted by a private licensed contractor after payment of the above fees, and his report must then be submitted to QESCO by the applicant. If all is approved and found to be in order, then t |
| Time to complete: | 15 days |
| Cost to complete: | PKR 1,400 |
| Comment: | Application is made on prescribed form alongwith documents:
(i) Evidence of ownership of, or, in case of a tenancy, a copy of the lease agreement in respect of the plot where the telephone is to be installed OR a copy of the utility bill in the name of t |
| Time to complete: | 21 days |
| Cost to complete: | PKR 11,200 |
| Comment: | BuildCo must file an Application on the prescribed form, along with the following documents
i. BuildCo's Certificate of Incorporation (In case of individual, his Computerized National I.D. Card)
ii. Resolution of BuildCo BOD, authorizing a representative |
| Time to complete: | 1 day (inspection takes place 5 days after submission of application) |
| Cost to complete: | no charge |
| Comment: | A WASA inspector will visit the proposed site, verify the contents of Application for water supply and prepare a feasibility. And report the matter to WASA. |
| Time to complete: | 1 dau |
| Cost to complete: | no charge |
| Comment: | Once the construction is completed in accordance with approved Construction Plans (Building Permit), the BuildCo would apply to TMA Quetta for final inspection and grant of Completion Certificate |
| Time to complete: | 1 day (inspection takes place between 7-15 days after submission of application) |
| Cost to complete: | no charge |
| Comment: | On Application for Completion Certificate, the General Building Inspector of the Area will visit the completed warehouse and would thoroughly inspect the same in light of approved plans and building byelaws. If he finds the place in order, he would report |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | On the report of GBI, the Final Completion Certificate would be issued to BuildCo for the warehouse concerned |
| Time to complete: | 15 days |
| Cost to complete: | PKR 350 (1% deduction of the PKR 35,000) |
| Comment: | Upon successful completion of Building, the Malba Security that is refundable is applied for. Upon examining the Completion Certificate, the challan to receive fee is made by the Revenue Officer TMA Quetta, whereafter fee is refunded
|