| Time to complete: | 15 days |
| Cost to complete: | PKR 250 |
| Comment: | The company must obtain a letter from the concerned authority confirming the title/land use physically fresh demarcated/dimensions of the plot along with the existence of any road widening/cut line/reservation. |
| Time to complete: | 53 days |
| Cost to complete: | PKR 10,000 |
| Comment: | BuildCo is required to submit an Environmental Impact Statement (EIS) for review and approval by the Director-General, Environment Protection Agency, Punjab, 4-Lytton Road, Lahore.
The statement shall include the following:
1. Name & location of industria |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 60 days |
| Cost to complete: | PKR 210,000 |
| Comment: | An application in the prescribed form is required to be submitted to the Tehsil Municipal
BuildCo must submit to the Sialkot Tehsil Municipal Administration (STMA) on the prescribed forms, accompanied by a NOC from the Environment Agency, an application |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | The building control officials/building inspector from STMA may pay surprise or notified visits to building site to check the progress of the construction and to ensure building control standards but normally these visits are made rarely in practice. In r |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | The building control officials/building inspector from STMA may pay surprise or notified visits to building site to check the progress of the construction and to ensure building control standards but normally these visits are made rarely in practice. In r |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | The building control officials/building inspector from STMA may pay surprise or notified visits to building site to check the progress of the construction and to ensure building control standards but normally these visits are made rarely in practice. In r |
| Time to complete: | 45 days |
| Cost to complete: | PKR 176,800 |
| Comment: | An application in the prescribed form will be required to be submitted to the Sialkot Electric Supply Corporation Limited along with the following documents for a new electricity connection:
(i) An attested copy of the applicant’s National Identity Car |
| Time to complete: | 3 days |
| Cost to complete: | no charge |
| Comment: | In case of a load in excess of 5 kw, an inspection should be conducted by a private licensed contractor, and his report must then be submitted to PESCO by the applicant. |
| Time to complete: | 15 days |
| Cost to complete: | PKR 1,400 |
| Comment: | An application in the prescribed form will be required to be submitted to the Pakistan Telecommunication Company Limited along with the following documents for a new telephone connection:
(i) Evidence of ownership of, or, in case of a tenancy, a copy of |
| Time to complete: | 25 days |
| Cost to complete: | PKR 1,200 |
| Comment: | An application in the prescribed form will be required to be submitted to the Tehsil water & sewerage board along with the following documents for a new water and sewerage connection:
(i) A copy of the approved building plan along with a copy of the lett |
| Time to complete: | 23 days |
| Cost to complete: | no charge |
| Comment: | After the building is completed a “notice of completion and permission for occupation” along with the Architects Certificate in the prescribed Form is require to be given. After receipt of this notice The STMA inspects the building to verify that it is ma |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Time to complete: | 7 days |
| Cost to complete: | no charge |
| Comment: | |