Albania

Getting Electricity in

Albania

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Albania.

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Albania to 185 other economies.

  • Standardized Company

  • Name of Utility: CEZ Shperndarje
  • City: Tirana
No. Procedure Time to Complete Associated Costs
1 Obtain approval from IQT for electricity connection

The customer has to request and obtain approval from the Central Technical Inspection (IQT) for the electricity connection.
Agency: Central Technical Inspection (IQT)
1 calendar day no charge
2 Submit application with electricity distribution utility CEZ Shperndarje and await external inspection

The customer submits the application with the electricity distribution utility CEZ in person. Documents submitted have to be in original or notarized. A declaration of conformity of the internal wiring signed by a licensed electrical engineer must be submitted with the application.

Agency: CEZ Shperndarje
50 calendar days no charge
3 Receive external site inspection and await estimate

After the customer has submitted the application, she/he has to wait for an estimate. The distribution utility CEZ sends a representative to the site to do an external inspection of the warehouse. Someone from the customer's party has to be present during the inspection. After the inspection, the distribution utility prepares the estimate for the connection and sends it to the customer.
Agency: CEZ Shperndarje
14 calendar days ALL 243,200.0
4 Obtain design by a private firm and get design approved by the Central Technical Inspection (IQT) and by the utility (CEZ), receive internal inspection by the Central Technical Inspection (IQT)

The design of the external connection works is done by an electrical design firm. The design has to be approved by the Central Technical Inspection (IQT) and by the utility. IQT is a state company. The internal wiring of the building is inspected only by IQT at the beginning of the connection works. The inspection can be requested anytime.
Agency: Electrical design firm/Central Technical Inspection (IQT)
93 calendar days USD 3,489.0
5 Receive external connection works by a private firm

The external connection works are carried out by an electrical contractor hired by the customer.
Agency: Electrical Contractor
14 calendar days USD 16,953.7
6 CEZ Shperndarje installs meter and inspects the internal wiring of the cabin and carries out the external connection works and opens the meter

The meter is installed after the connection works are finished. The meter is installed and opened by the distribution utility CEZ. Before the opening of the meter, the utility is carrying out an inspection of the internal wiring of the cabin of the transformer and of the external connection works.
Agency: CEZ Shperndarje
5 calendar days no charge