The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Name of Utility: Bhutan Power Corporation Ltd
  • City: Thimphu

About This Topic

To see indicator data for all economies, see the Getting Electricity page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Submit application to Bhutan Power Corporation and await site inspection

Application needs to be submitted in person, with building drawings. No notarization or application fee is required

Agency: Bhutan Power Corporation
14 calendar days no charge
2 Receive site inspection and await estimate

Utility conducts external site inspection for providing estimate.

Agency: Bhutan Power Corporation
15 calendar days no charge
* 3 Receive internal wiring inspection from Bhutan Power Corporation

Utility inspector conducts inspection of all internal wiring, completes a test report form on site and gives it to customer/electrician. This report needs to be submitted by customer to utility office while making payment.

Agency: Bhutan Power Corporation
15 calendar days no charge
4 Request and receive excavation permit from Dept. of Roads for excavation

Customer applies for and receives excavation permit from the Dept of Roads.

Agency: Department of Roads
3 calendar days no charge
5 Customer purchases equipment and conducts external connection works

External connection works includes cost of 250 KVA substation, rabbit conductor, cables, poles, line extension costs. Before starting any works, the utility obtains excavation permit from the Dept of Roads.

Agency: Electrical contractor
53 calendar days BTN 1,153,474.9
6 Bhutan Power Corporationinstalls meter installation and electricity starts flowing

The utility installs the meter, the customer pays the meter deposit charge and electricity starts flowing.

Agency: Bhutan Power Corporation
15 calendar days BTN 6,000.0
* Takes place simultaneously with another procedure.