No. Procedure Time to Complete Associated Costs
1 Submit application to Bhutan Power Corporation and await site inspection

Application needs to be submitted in person, with building drawings. No notarization required. No application fee.
Agency: Bhutan Power Corporation
14 calendar days no charge
2 Receive site inspection and await estimate

Utility conducts external site inspection for providing estimate
Agency: Bhutan Power Corporation
15 calendar days no charge
* 3 Receive internal wiring inspection from Bhutan Power Corporation

Utility inspector conducts inspection of all internal wiring, completes a test report form on site and gives it to customer/electrician. This report needs to be submitted by customer to utility office while making payment.
Agency: Bhutan Power Corporation
15 calendar days no charge
4 Request and receive excavation permit from Dept. of Roads for excavation

Customer applies for and receives excavation permit from the Dept of Roads
Agency: Department of Roads
3 calendar days no charge
5 Customer purchases equipment and conducts external connection works

External connection works includes cost of 250 KVA substation, rabbit conductor, cables, poles, line extension costs. Before starting any works, the utility obtains excavation permit from the Dept of Roads
Agency: Electrical contractor
42 calendar days BTN 1,153,474.9
6 Bhutan Power Corporation conducts testing of transformer, installs meter and electricity starts flowing

The utility installs the meter, the customer pays the meter deposit charge and electricity starts flowing
Agency: Bhutan Power Corporation
15 calendar days BTN 6,000.0