Burkina Faso

Dealing with Construction Permits in

Burkina Faso

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: XOF 260,120,000
  • City: Ouagadougou

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Legalize copy of deed (proof of right to possession)

One can notarize a copy of the title at any notary.

Agency: Notary
1 day XOF 200
2 Obtain soil survey from National Laboratory of Building and Public works

The soil survey is carried out by the National Laboratory of Construction and Public Works (Laboratoire National des Batiments et Travaux Publics Burkina). The purpose of this study is to analyze and inform the construction company of the parameters for the foundations (what type of foundations are required, how deep in the soil should they dig, what is the quality of the soil etc).

The fees depend on the size of the building, and according to the arrêté conjoint N 2008-066/MHU/MATD/MEF/MID and the circulaire N 10-01195/MID/SG/LNBTP, the cost of the soil survey from National Laboratory of Building and Public Works is XOF 300,000


Agency: Laboratoire National des Batiments et Travaux Publics Burkina- LNBTP
30 days XOF 300,000
3 Obtain fire safety study from a licensed fireman or competent private agency

To obtain this study, one needs to make a request with a licensed fireman (‘personne agree’ - pompier) or at the agency SCEPSI – ‘Societe Commerciale d’Etudes, de Prevention et de Securite Incendie’. The document would take about 1-2 weeks. The fees depend on the size of the building. The fire safety study fees for Category 3 buildings (e.g. warehouse) would be CFA 165,000.

Agency: Licensed Fireman
10 days XOF 165,000
4 Obtain building permit at CEFAC one-stop shop and pay fees

Documents obtained from the first 3 procedures (Soil survey, legalized copy of ID and land title, and architecture plans) are brought to CEFAC. The files will be analyzed by one of CEFAC’s two experts on construction permits. If the agent finds that the application package in incomplete, he/she will inform the client before sending the application to other agencies and will ask him to provide the missing materials.

The following documents must accompany an application to construct a warehouse (category C):

An application form, with a 200 fcfa stamp fee
A copy from the RCCM of the company’s status
A legalized copy of the land title
A demarcation plan
An architectural study report established by an recognized by the Order of Architects
An engineering report detailing the construction requirements

When the application package is complete, the file is ready to be submitted to the CEFAC commission. Four agencies are represented in this commission: The fire department, the tax office, the municipality, and the Urban Planning Ministry (Ministere de l’Habitat et l’Urbanisme). The committee meets every fifteen days. By law, they have to get back to the applicant within 18 days so a decision is delivered every 20-30 days. The commission can reject an application for many reasons (including wrong zoning) but applicant can only appeal once. , An application is rarely rejected. Even in cases when the application requires further information, the commission gives a conditional permit, allowing the applicant to work on the remaining elements. The permit given by the commission is valid for 5 years and can be renewed once.


Agency: Centre de Facilitation des Actes de Construire (CEFAC)
20 days XOF 207,024
5 Receive excavation inspection

The laboratory subcontracts with a private laboratory, which conducts weekly inspections. It is assumed that the project will be built in 30 weeks.

Agency: National Laboratory of Building and Public Works
15 days XOF 130,060
6 Receive foundation inspection

The laboratory subcontracts with a private laboratory, which conducts weekly inspections. It is assumed that the project will be built in 30 weeks.

Agency: National Laboratory of Building and Public Works
1 day no charge
7 Receive concrete work inspection

The laboratory subcontracts with a private laboratory, which conducts weekly inspections. It is assumed that the project will be built in 30 weeks.

Agency: National Laboratory of Building and Public Works
1 day no charge
8 Obtain Certificate of Comformity



Agency: Centre de Facilitation des Actes de Construire (CEFAC)
20 days no charge
* 9 Request water connection



Agency: Water Authorities
1 day XOF 2,000
* 10 Pay fees and obtain connection



Agency: Water Authorities
14 days XOF 100,000
* 11 Request telephone connection



Agency: ONATEL
1 day no charge
* 12 Pay fees and obtain telephone line



Agency: ONATEL
7 days XOF 20,000
* Takes place simultaneously with another procedure.