China

Dealing with Construction Permits in

China

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: CNY 1,279,322
  • City: Shanghai

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Submit application to obtain approval of the project proposal from the District Development and Reform Commission

To request approval of the project proposal, BuildCo must submit the following documents to the Municipal Development and Reform Commission:
- Letter of application.
- Project proposal, with feasibility study report compiled according to government specifications.
- Land use right.
- Construction location map.
- Business certificate.

The commission will consult with the municipal authorities overseeing land use, planning, and other governmental functions: education, transportation, fire safety, health and sanitation, relics preservation, landscape planning, people's defense, energy efficiency, seismic monitoring, and water irrigation and management. The commission deals with all departments internally.

The feasibility study report, issued by this agency, is required for project investments worth over CNY 10 million. Thus, the report does not apply in the case considered here.

There is no unified time limit for examining and approving the project conducted by the Municipal Development and Reform Commission. For this procedure, the time frame is determined by the particulars of each project. The time frame may vary between 2 to 4 weeks.

Agency: Municipal Development and Reform Commission
21 days no charge
* 2 Request and obtain the approval of request of construction project planning and design from the Competent Department of Urban Planning

The Municipal Commission of Urban Planning evaluates the project impact on city planning. Inspection and mapping may be conducted before the commission issues an opinion letter on location selection and enquiry forms for the authorities that the commission deems necessary to be consulted.

To request approval for construction on self-owned land, BuildCo must submit the following documents:
- Attestation on land use rights, which may be one of these three documents (a) land use certificate of state-owned land (国有土地使用证); (b) planning permit for using land for construction purposes (建设用地规划许可); and (c) certificate of collectively owned land use rights (集体土地使用证).
- A completed application form (planning permission of construction project) stamped with BuildCo’s seal.
- Introduction of the planned project, including zone area, construction purpose, project feature, and so forth.
- Planning drawings (including major technical indicators).
- Basic cadastral map with designed construction location marked out.
- Topographic map (地形图).
- Title certificate of the land and its attached drawing.

Ensuring that planned construction complies with city requirements planning, the commission examines the documents and proposes design requests.

As a result of this procedure, the relevant municipal construction commission will give the applicant an identification number that allows the applicant to track the progress made on the applicationwhen the applicant submit reports on the approved construction project; this occurs after Procedure 2.

Agency: Municipal Commission of Urban Planning
28 days no charge
* 3 Request and obtain the approval on planning and design project for construction (建设工程规划设计方案批复) and the notification on the review of the design plan (审定设计方案通知书) from the Construction Department (市规划委员会)

After obtaining the approval of planning request, BuildCo should apply with the Planning Bureau for the approval of the construction planning and design project (建设工程规划设计方案批复). The following documents are required for apply this approval:
- Application form, Planning and design project for construction.
- Topographical map(地形图).
- Ichnographic map(平面图).
- Scheme drawing (方案图)and instruction of design.
- Form, Area of layers (分层面积表).
- Approval of the feasibility study report or other relevant approval.
- Approval of request of construction project planning and design (建设工程规划设计要求通知单).
- Other relevant documents and drawings required in the notice of request for construction project planning and design.

The time line is 28 days. There is no charge for this approval.

Agency: Municipal Commission of Urban Planning
28 days no charge
4 Request and obtain the Planning Permit of Using Land for Construction Purposes


To request a land-use planning permit, the documents to be filed include
- Application for project planning permit (form sealed by BuildCo).
- Planning opinion and attached map.
- Project proposal, including feasibility report and other documents approved by the municipal planning authority.
- Notice of opinion on construction location and affixed maps or, otherwise, the agreement of the transfer of right for state-owned land and affixed maps.
- Cadastral map.
- Approval of construction design and maps, if the plan has been approved.

The authority should notify the applicant whether revisions are needed within 5 days. The time for this procedure is 40 working days. This procedure occurs after the “notification of the review of design plans” is issued by the municipality.

Agency: Shanghai District Urban Planning Administration Bureau
60 days no charge
* 5 Request and obtain the land using permit for construction from State Land, Resources, and Housing Agency

The Shanghai Housing, Land, and Resource Administration Bureau reviews requests for the land-use construction permit (建设用地批准书), including the following documentation:
- Land use planning permit for construction purposes (建设用地规划许可证).
- Pole setting notice (用地钉桩成果通知单)
- Plan of building progress.
- Application for land-use permit.

Agency: State Land, Resources, and Housing Agency
10 days no charge
6 Request and obtain an environmental evaluation

In the case considered here, BuildCo must submit an environmental impact assessment (环境影响报告表). Effective January 1, 2006, the approval of environmental evaluation form can be obtained at no cost in 30 days.

Agency: Bureau of Environmental Protection
30 days no charge
* 7 Request and obtain construction procject planning permit

Documents needed for construction on the self-owned land include the following:
- Construction plan documents, approved by the Municipal Development and Reform Commission (not required for new buildings less than 300 sq. m. and renovation projects less than 3,000 sq. m.).
- Application form (planning permission for a construction project), stamped with BuildCo seal.
- Notice on the review of the design plan, and the attached drawings.
- Building design drawings.
- Agreements and documents required by the Notice on the review of the design plan.
- Topographic map (地形图).
- Ichnographic map (平面图).
- Construction map (建筑施工图).
- Groundwork construction ichnographic map (基础施工平面图), groundwork detail drawing(基础详图及), and piling plan drawing(桩位平面布置图).
- Ichnographic sketch map used for public purposes.
- Approval documents on primary proposal of the construction project.
- Title certificate of the land and its attached drawing.
- Construction budget plan.

The authority issues the permit of project planning or a notice of revision on building drawings. Cost is calculated at 0.1%–0.3% of estimated construction value, and the percentage is smaller if the building cost is larger.

Agency: Competent Department of Urban Planning
35 days CNY 1,319
8 Request and obtain certificate of safety operation on construction project at the Safety and Quality Supervision Office of the Municipal Construction Commission

All project construction companies must obtain the certificate of safety operation. To obtain it, BuildCo must file the annual building plan and the construction planning permit with the Safety and Quality Supervision Office of the Municipal Construction Commission. This requirement is set by the Notice on Strengthening the Approval of Certificate of Safety Operation on Construction Project, issued by the Department of Construction, effective June 24, 2005.

The time line to complete this procedure is 45 days after filing. The cost is CNY 20. According to the Implementation Regulations for Construction Project Building Permits of Safety Operation of Shanghai (No. 161, dated March 2006), (《上海市建筑施工企业安全生产许可证管理实施细则》), companies can apply through the Commission’s Web site. The request is processed in 10 working days.

Agency: Municipal Construction Commission (Safety and Quality Supervision Office)
1 day CNY 20
9 Request and obtain evidence of capital from bank



Agency: Commercial Bank
1 day no charge
* 10 Hire an authorized supervision agency

There is no uniform price for hiring a supervisor, but the government will normally impose a cap rate or price range. The cost should be calculated as follows:
1. Designing step: if the budgetary estimate of the project design is less than CNY 5,000,000, the cost is calculated as 0.44 % (1,319,017.93 x 0.44%= CNY 5,803.6) of the budgetary estimate of the project design.
2. Building and repairing step: if the budgetary estimate of the project building and repairing is less than CNY 5,000,000, the cost is calculated as 3.3% (1,319,017.93 x 3.3% = CNY 43,527.59CNY) of the budgetary estimate. The new value is CNY 43,527.59 + CNY 5,803.6 = CNY 49 331.19. Adtionally builders need to pay CNY 78,036 (CNY 60 per square feet) for designs to be presented to the People's Civil Defense office.

These calculations are according to the Notice on the Standard of Industry-directed Price for the Construction Supervision Agency Fees of Shanghai’ (Hu Jiang Jiang Xiezi [2001], No.20, effective January 1, 2002).

Agency: Authorized Supervision Agency
2 days CNY 126,057
* 11 Register construction drawings at the People’s Civil Defense office

Commercial warehouses do not need approval by the People's Civil Defense Office. However, the builder still needs to present the design of the warehouse for registration and filing. This needs to be prepared by an authorized supervision agengy.

Agency: People’s Civil Defense Office
1 day no charge
* 12 Review of construction drawings by Shanghai City Appearance & Environmental Sanitation Administration Bureau



Agency: Shanghai City Appearance & Environmental Sanitation Administration Bureau
10 days no charge
* 13 Review of construction drawings by Fire Protection Bureau



Agency: Fire Protection Bureau
20 days no charge
* 14 Review of construction drawings by Shanghai Police and Traffic Police District Level Team



Agency: Shanghai Police and Traffic Police District Level Team
25 days no charge
* 15 Receive review of building drawings by a building drawing examiner authorized by the Shanghai Construction Project Document Review Center (Construction Committee) and obtain a letter of notice

The building drawing review and fee collection occur simultaneously with the issuance of the construction project planning permit.

Agency: Shanghai Construction Project Document Review Center
20 days no charge
* 16 Register for direct contracting of construction with the District Tendering Office



Agency: District Tendering Office
1 day no charge
* 17 Have the building contractor and supervisor seal the application form



Agency: Building Contractor and Supervisor
1 day no charge
* 18 Pay the fees for funds of concrete (散装水泥基金) and energy-saving wall materials (节能墙体材料) with the Office of Building Materials of the Municipal Construction Commission

The fee for the concrete fund is CYN 4 per ton. The fee for the new energy-saving wall material fund depends on the type of construction:
- Civil: CYN 8 per sq. m.
- Industrial: CYN 10 per sq. m.

There is no charge for filing an application. BuildCo does not need to pay the fund for the new energy-saving wall material. After BuildCo completes construction, the Office of Building Materials charges for the clay brick funds, according to the size and number of clay bricks used in construction:
- 24 centimeter clay brick: CNY 0.085 per brick.
- 20 centimeter clay brick: CNY 0.060 per brick.

Fee schedule for concrete fund:
- 500 tons or under: CNY 3 per ton.
- More than 500 tons: CYN 2 per ton.

The time line is 1 day for concrete and 7 days for energy-saving wall materials.

Agency: Municipal Construction Commission (Office of Building Materials)
8 days no charge
19 Request and obtain building permit

To request a building permit, BuildCo must file the following documents:
- Land-use permit for construction purpose (建设用地许可证).
- Planning permit for the construction project (建设工程规划许可证).
- Building contract.
- Building drawings and examination documents (施工图设计文件审查通知书和施工图纸).
- Building organization plan (施工组织设计), with the opinion from the general supervisor or the lead project technician.
- Notification of qualify monitoring and safety monitoring (质量监督通知书、安全监督通知书).
- Contract of supervision (监理合同).
- Evidence of capital.
- Building permit applications (建筑工程施工许可申请表) (two copies).
- Building plan for the year (年度施工计划).
- Filing notice with the People's Defense Office.
- Evidence of payment of fees (四源费统一收费证明).
- Evidence of payment of concrete fund and energy-saving fund (建筑节能与发展新型墙体材料转项用费、散装水泥转项基金).
- Registration notice from the Municipal Statistics Bureau (统计局注册登记通知书).
- IC card for construction project.
- Construction contract and anticorruption agreement (form agreement between the owner and the contractor for certain anticorruption commitments) (copy).

The office registers on BuildCo’s behalf for quality and safety monitoring and issues a notice. The statutory time limit for this procedure is 15 working days.

Agency: Municipality
21 days CNY 4,552
* 20 Receive on-site inspection by the Construction Commission

No time limits apply for inspections. The approximate waiting time is 5 days.

Agency: Construction Commission
1 day no charge
21 Receive "Four-Party" Inspection

This procedure is called a four-party inspection (四方验收). The four parties include the site inspector, the designer, the builder, and the supervisor.
1 day no charge
* 22 Request and receive inspection of the completed construction from the planning department

To request a final inspection, BuildCo must file the following documents:
- Application form for building construction permit.
- Planning permit for the construction project (建设工程规划许可证).
- Bank attestation on capital (资金入账凭证).
- Evidence of water connection, power connection, road access, and ground unknited (三通一平).
- Construction contract with contractor and probity agreement (廉洁协议).
- Supervising contract.
- Certificate of quality and safety operation.
- Bid winning award notice for exploration, design, and construction.
- Approval of construction drawings and examination of design documents.

Agency: Planning Department
10 days no charge
* 23 Request and receive fire department inspection upon building completion



Agency: Fire Department
15 days no charge
24 Request opinion on whether construction project is lightning-proof

To obtain an opinion, BuildCo must file the following with the fire department:
- Application for fire department inspection of the completed construction.
- Inspection report of fire control establishment, if any.

Agency: Fire Department
14 days no charge
25 Request and obtain certificate of the completed construction from the fire department

The time limit is 17 working days from the receipt of application (according to Web site information for the Public Security and Fire Prevention Authority). In practice, the application process takes longer.

Agency: Fire Department
15 days no charge
* 26 Request and receive inspection of the completed construction from the environmental protection department

To receive a final environmental inspection, BuildCo must submit these required documents:
- Supervisory report from the completed construction inspection.
- Application for completed construction inspection.
- Approval of trial production.
- Approval of evaluation on environmental impact.

The time limit is 30 days from the receipt of application, according to the Environment Protection Bureau Web site.

Agency: Environmental Protection Department
30 days no charge
* 27 Request and receive inspection on construction completion (竣工备案) and inspection from the Municipal Construction Committee

Within 15 days after the building passes inspection, BuildCo must file the following documents with the Municipal Construction Commission:
- Filing form for inspection of completed construction.
- Inspection report of the completed construction (including all project information and acknowledgments of design, building, and supervisory parties).
- Occupation permits, issued by the planning, police and fire, and environmental departments.
- Acknowledgment of the city construction dossier department.
- Permit, issued by the People's Defense Office.
- Quality warranty, issued by the builder.
- Completion inspection report, IC card of construction project, and use permit (issued respectively by the Urban Planning Authority, Public Security Authority, Fire Prevention Authority, Environmental Protection Bureau, Antithunder Center), concrete fund settlement application, and documents on quality auditing fare settlement.

This procedure must be completed on the day of application, provided that the documents required for submission are complete. There is no charge for this procedure.

Agency: Municipal Construction Committee
7 days no charge
28 Request and obtain certificate of completion and certificate of fiinal inspection from the Municipal Construction Commission

Within 15 days after the building passes the inspection, BuildCo must file the following documents with the Municipal Construction Commission:
- Filing form of inspected completed construction.
- Inspection report of the completed construction (including all project information and acknowledgment of the design, building, and supervisory parties).
- Occupation permits, issued by the planning, police and fire, and environmental departments.
- Acknowledgment of the city construction dossier department.
- Permit, issued by the People's Defense Office.
- Quality warranty, issued by the builder.
- Opinion on inspection and acceptance of lightning-proof construction project (建设项目防雷工程验收意见书).
- Application form for fund of concrete (散装水泥专项基金结算申请表).
- Relevant documents of paid fees of quality supervising (有关质监费结算的资料).
- IC card of construction project.
- Completion inspection report, IC card of construction project, use permit (issued respectively by Urban Planning Authority, Public Security Authority, Fire Prevention Authority, Environmental Protection Bureau, Antithunder Center), concrete fund settlement application, and documents on quality auditing fare settlement.

This procedure must be completed on the day of application, provided that the documents required for submission are complete. There is no charge for this procedure. The statutory time limit for this procedure is 15 working days.

Agency: Municipal Construction Committee
21 days no charge
29 Request water and sewage connection

The water and sewage connection fee depends on the actual project size (including the price of labor and materials). A budget is a must.

The application procedure lasts at least 1–2 months and usually takes 3–4 months.

Agency: Municipal Water Bureau
1 day no charge
* 30 Receive water and sewage inspection

Upon receiving the water supply application, the water service crew conducts on-site surveys within 7 days. The completion of water supply is determined by construction conditions. As for sewage licensing, the Municipal Water Bureau needs 20 days after BuildCo submits the project approval and other documents on the sewage facility design to conduct a preliminary inspection. After completing the inspection and trial operation, the bureau requires 20 days to examine the results of the facility and grant approval.

Agency: Municipal Water Bureau
1 day no charge
* 31 Receive connection to water and sewage services



Agency: Municipal Water Bureau
49 days no charge
* 32 Request and receive connection to telephone

The charge may vary between CNY 140 and CNY 310.

Agency: Shanghai Telecom Co., Ltd.
14 days CNY 200
* 33 Register building with Real Estate Registry

The warehouse considered here should fall into the category of nonresidential real property, in which case the registry procedure will take 20 days from receipt of the application. The cost is calculated according to the actual property value. In this case, considering the assumption that the value exceeds 1 million, the registry fee rate should be 0.03%, or about CNY 384. Before selling the building, the property must be registered and the certificate obtained.

Agency: Real Estate Registry
30 days CNY 550
* Takes place simultaneously with another procedure.