Comoros

Getting Electricity in

Comoros

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Comoros.

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Comoros to 185 other economies.

  • Standardized Company

  • Name of Utility: MaMWE
  • City: Moroni
No. Procedure Time to Complete Associated Costs
1 The client submits an application to Ma-MWE and awaits estimate of connection fees

The following documents are needed along with the application:
- ID card
- Connection authorization from MA-MWE (or from the closest pole's owner)
- Property title (in practice, this has never been requested)
- A plan of the installations (in practice, this has never been requested)
Agency: MA-MWE
10 calendar days KMF 5,000.0
* 2 The client obtains external inspection by Ma-MWE

An inspection of the site is needed to carry out a technical study of the connection works.
Agency: MA-MWE
1 calendar day no charge
3 The client obtains external works and final connection from Ma-MWE

Only MA-MWE is in charge of the external works (which, in this case, consist of installing an overhead substation).
The material for this case is usually not available in the utility's stock, and it has to be imported (especially for the transformer), often from France. The material to be installed includes the overhead transformer and its accessories (on both sides of the transformers), cables, poles (a pole every 70 meters), joints, panel, and meter.
The excavation permit is obtained by the utility from the relevant public agencies.
No inspection of the internal wiring is carried out.
Agency: MA-MWE
110 calendar days KMF 7,089,550.5
* Takes place simultaneously with another procedure.

Explore Economy Data


- OR -