Comoros

Getting Electricity in

Comoros

Listed below are the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building.

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Name of Utility: MaMWE
  • City: Moroni

About This Topic

To see indicator data for all economies, see the Getting Electricity page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 The client submits an application to Ma-MWE and awaits estimate of connection fees

The following documents are needed along with the application:
- ID card
- Connection authorization from MA-MWE (or from the closest pole's owner)
- Property title (in practice, this has never been requested)
- A plan of the installations (in practice, this has never been requested)

Agency: MA-MWE
10 calendar days KMF 50,000.0
* 2 The client obtains external inspection by Ma-MWE



Agency: MA-MWE
1 calendar day no charge
3 The client obtains external works and final connection from Ma-MWE

Only MA-MWE is in charge of the external works (which, in this case, consist of installing an overhead substation).
The material for this case is usually not available in the utility's stock, and it has to be imported (especially for the transformer), often from France. The material to be installed includes the overhead transformer and its accessories (on both sides of the transformers), cables, poles (a pole every 70 meters), joints, panel, and meter.
The excavation permit is obtained by the utility from the relevant public agencies.
No inspection of the internal wiring is carried out.

Agency: MA-MWE
110 calendar days KMF 7,911,740.4
* Takes place simultaneously with another procedure.