Congo, Rep.

Getting Electricity in

Congo, Rep.

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Congo, Rep..

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Congo, Rep. to 185 other economies.

  • Standardized Company

  • Name of Utility: Société Nationale d'Electricité (SNE)
  • City: Brazzaville
No. Procedure Time to Complete Associated Costs
1 Client submits application for connection at Societe National d'Electricite (SNE) and await estimate and technical study

The client submits the application for connection at the utility. The utility conducts a technical study and prepares an estimate. The utility is conducting a site visit, however the client does not have to be present. The utility sends the estimate to the client after the site visit.
Agency: Société Nationale d'Electricité (SNEL)
7 calendar days no charge
* 2 Receive external inspection by Société Nationale d'Electricité (SNE)

SNE conducts an external site visit to prepare the estimate and the technical study. However, no one of the client's party has to be present. After the technical study, SNE gives a quote to the customer depending on material and workforce available. SNE also gives to the client a list of companies which can do the external works.
Agency: Société Nationale d'Electricité (SNEL)
1 calendar day no charge
3 Hire a licensed electrical contractor, purchase material and carry out external connection works

The client hires a licensed electrical contractor. The contractor purchase the material and conducts the external connection works.
Agency: Electrical Contractor
120 calendar days XAF 58,629,550.0
* 4 Obtain excavation permit at the Municipality

The client needs to obtain an excavation permit at the Municipality to cross the road
Agency: Municipality
60 calendar days no charge
5 Obtain inspection of the works, installation of the meter and final connection by Societe National d'Electricite (SNE)

Once the works are done, the electrical contractor informs the utility. The utility comes to the warehouse to inspect the works and to do the final connection. The meter is installed at the same time.
Agency: Societe National d'Electricite (SNE)
7 calendar days no charge
6 Receive and sign supply contract

After the inspection, the client calls the utility and goes to the commercial service department to sign the supply contract and pay an advance on the consumption. The advance on consumption is calculated with a formula and is given back at the end of the supply contract.
Agency: Societe National d'Electricite (SNE)
1 calendar day XAF 704,987.2
* Takes place simultaneously with another procedure.

Explore Economy Data


- OR -