Dominica

Dealing with Construction Permits in

Dominica

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: XCD 240,611
  • City: Roseau

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
* 1 Obtain Outline Planning Permission



Agency: Development and Planning Corporation (D & PC)
56 days XCD 50
2 Obtain Planning permission



Agency: Development and Planning Corporation (D & PC)
90 days XCD 1,000
3 Request and receive inspection of building setout with approved setbacks

According to the building code, nine inspections should be conducted during the construction process. Each inspection occurs within 48 hours of being requested by the contractor for review. However, only three occur in practice. There are no fees for the inspections.

Agency: Development and Planning Corporation (D & PC)
1 day no charge
4 Request and receive inspection of substructure (foundation)



Agency: Development and Planning Corporation (D & PC)
1 day no charge
5 Request and receive inspection of framing for roof



Agency: Development and Planning Corporation (D & PC)
1 day no charge
6 Request for water-sewage connection



Agency: Dominica Water and Sewage Company (DOWASCO)
1 day no charge
* 7 Receive water - sewage inspection



Agency: Dominica Water and Sewage Company (DOWASCO)
1 day no charge
* 8 Obtain water - sewage connection



Agency: Dominica Water and Sewage Company (DOWASCO)
14 days XCD 240
* 9 Obtain a fixed telephone line



Agency: Cable and Wireless
3 days XCD 150
* Takes place simultaneously with another procedure.