Dealing with Construction Permits in
Assiut - Egypt, Arab Rep.
Below is a detailed summary of the procedures, time and costs to build a warehouse. This includes obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections.
The information appearing on this page was collected as part of the Doing Business subnational project in Egypt, Arab Rep.. Download this Doing Business report or explore other cities and topics.
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Obtain cadastral documents from the Survey
department of the Assiut Governorate
The measurement specification documents include: cadastral delimitation
statement, cadastral map signed by survey authority, and colored cadastral map
taken by airplane for the construction site.
|
7 days
|
EGP 110
|
| * 2 |
Obtain technical approvals from an independent
syndicate engineer
These documents include: approval of the colored cadastral map,
approval of probe estimation, execution supervision certificate (cost EGP 250-350),
approval of architectural drawings (cost EGP 150-200), accounting book, report confirming
the quality of the building foundations (cost EGP 250 to 300), and acquiring a
soil investigation report (cost EGP 1,000).
|
5 days
|
EGP 1,750
|
| 3 |
Submit building permit application to Licensing
department of the Alexandria governorate
The applicant must submit an extensive list of documents (included the
ones described in the previous procedures) to the Licensing department. The list is
as follows:
a. Original ownership contract of the plot of land (notarized)
b. Measurement specification statement from the Survey department
c. Survey plan “air photography” specifying location. Such survey plan shall be
approved by an accredited syndicate engineer
d. Alignment license from the Urban planning department of Assiut governorate
e. Probe estimation approved by a syndicated engineer
f. Execution supervision certificate from a syndicate engineer or consultant engineer
in case the building’s value is more than EGP 1,000,000.00
g. A receipt attesting the payment of the duty related to the examination of the
drawings and details
h. A general drawing of the site at a drawing scale of a minimum 1:1000 that indicate
the boundaries and dimensions of the land of the site for which the permit is
required, together with the total land area, and that part on which construction
is requested, as well as the facing roads and their widths
Ministerial Decree 92 of 2006, issued by the Ministry of Housing, Utilities, and Urban-
Communities, reduced the number of files necessary to request a building permit.
Consequently, the following documents are required: one file containing a copy
of the architectural drawings in respect of the horizontal projections of floors and
facades, a vertical section indicating the building height as to the road’s zero level
and the structural drawings of the foundations, columns and the enforced ceilings
together with copies of the structural calculation notes. All drawings shall be signed
by an accredited engineer. Also, a report from a structural engineer must be submitted
confirming that the structural skeleton and the foundations of the building will
tolerate the required licensed works, are in compliance with safety provisions, will resist
the natural disasters, are in accordance with the Egyptian construction standards, and illustrate the soil composition at the site. In case of any elevation or modification
it is required to submit a report from a construction consultant accredited for no less
than 25 years indicating that an inspection and a study of the existing buildings have
proven that they will tolerate the applicable loads.
Law 4 of 2006 reduced the fee to obtain a building permit from 1% of construction
cost to 0.2%. Upon submitting the application file, building permit applicants in
Assiut pay the permit fee at the cashier's office in the Governorate.
|
1 day
|
EGP 2,000
|
| 4 |
Receive inspection and obtain project clearance
from Civil defense bureau
Once the permit application is submitted to the District bureau, it is
passed on the Civil defense bureau for clearance. The Civil defense bureau checks
that the design drawings comply with national fire safety regulations. The clearance
from the Civil defense bureau. The clearance takes between 1 to 2 months depending
on the amount of follow up.
|
45 days
|
No cost
|
| * 5 |
Obtain project clearance from the
Water authority
|
30 days
|
No cost
|
| * 6 |
Obtain project clearance from the
Electricity authority
|
30 days
|
No cost
|
| * 7 |
Receive inspection prior to permit issuance from
the Licensing office
An inspector from the municipality inspects the proposed construction
site to verify the information included on the application.
|
1 day
|
No cost
|
| * 8 |
Pay real estate tax at the Tax authority
|
1 day
|
EGP 30
|
| 9 |
Obtain building permit from the Licensing office
Law 106 of 1976 establishes a 30 day statutory time limit for issuing
building permits, but these 30 days are counted only after all preliminary approvals
are obtained.
After the technical portion of the file is reviewed, the Licensing office of the Assiut
governorate sends the file to the Social security administration and the company’s
chosen insurance provider to ensure that the builder has purchased insurance for
the project. After this check is completed, the builder can pick up its building permit
from the governorate.
|
30 days
|
No cost
|
| 10 |
Receive on-site inspection from the Licensing office
Inspections occur rarely in Assiut. The number of inspections a construction
site receives during construction varies depending on the visibility of the
project. For a smaller scale project such as a warehouse, inspectors may only visit the
site once during construction.
There are often informal fees paid to the inspector, however the standard official fee
for each inspection is EGP 20.
|
1 day
|
EGP 20
|
| 11 |
Receive final inspection by a committee from the
Licensing office
Once construction is completed, a committee from the Licensing office
makes a final inspection to certify that the warehouse conforms to the specifications
outlined in the building permit.
|
1 day
|
EGP 20
|
| 12 |
Obtain letters from Licensing office about water
and sewage connection and about electricity cables installation
As described above the company must obtain approval letters from the
municipality necessary for obtaining utility connections.
|
1 day
|
No cost
|
| 13 |
Obtain certificate of natural disaster from an
independent syndicate engineer
A supervising engineer issues the certificate of natural disaster. The cost
reflects the fees for issuing the certificate.
|
7 days
|
EGP 102
|
| 14 |
Obtain the water and sewerage connection from the Assiut water authority
The company submits an application to the Municipal department to
obtain a letter to be provided to water company. Then, the company submits an
application to the competent water authority, along with the original license and a
copy of the building permit. Fees include approximately EGP 10,000 for the water
connection and EGP 5,000 for the sewerage connection.
|
30 days
|
EGP 15,000
|
| * 15 |
Apply for an electricity connection with the
Assiut electricity distribution company
|
1 day
|
No cost
|
| * 16 |
Receive electrical inspection
The Electricity authority inspects the construction site to provide an
estimate for the cost.
|
1 day
|
No cost
|
| * 17 |
Obtain electricity connection
Connection fees include the laying down of the cables.
|
14 days
|
EGP 15,000
|
| * 18 |
Obtain phone connection from Telecom Egypt
The company should submit the following documents:
a. Title deed for the unit, or lease contract if it is not owned by the applicant;
b. Copy of applicant’s ID;
c. Operation license for factories, stores, commercial stores and workshops.
|
14 days
|
EGP 850
|
| 19 |
Register the building with the real estate registry
The company must submit a form as well as the building permit for the
warehouse and the primary purchase contract of the land on which the warehouse
had been built.
Law 83 of 2006 amended Decree no. 70 for the year 1964 to decrease registration
fees to a flat fee of EGP 2,000 instead of the fee being a percentage of the building
value.
|
30 days
|
EGP 2,000
|
* Takes place simultaneously with another procedure.
Data snapshots