Finland

Getting Electricity in

Finland

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Finland.

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Finland to 185 other economies.

  • Standardized Company

  • Name of Utility: Helsinki Energy
  • City: Helsinki
No. Procedure Time to Complete Associated Costs
1 Submit application and certification from electrician to Helsinki Energy

An application can not be submitted online at present. The applicant must fill out one form (the contract for getting connected to the distribution grid) and send us all the necessary blueprints of the buildings internal wiring. The blueprints have to be approved by us before the building is connected to the grid.
Agency: Helen Electricity Network
1 calendar day no charge
2 Customer purchases material, and conducts external connection works

The customer needs to purchase and install the connection cable from the building to the perimeter wall, since the utility only does external connection works, and everything inside the boundary wall of the building is the customer’s responsibility. The meter is installed only after the connection cable is installed.
Agency: Helen Electricity Network
3 calendar days EUR 3,000.0
3 Electrician contacts Helsinki Energy representative to discuss details of connection and Helsinki Energy conducts external connection works

The customer's electrician submits a document where he states that all the wiring has been done according to the rules and regulations. No outside agency needs to bee contacted when inspecting the internal wiring of the type of building that is described above. The person in charge of the wiring has to be a certified electrician and have the licenses that are required to do inspections. The electricians do not have to be registered with our company nor do we check if they are certified.
Agency: Helen Electricity Network
30 calendar days EUR 7,640.0
4 Sign supply contract with retailer

The customer has a choice of retailers for electricity supply. In the case of most retailers, the application is done online, and no paperwork needs to submit.
Agency: Helen Electricity Network
1 calendar day no charge
5 Electrician informs Helsinki Energy, meter is installed by utility subsidiary, and electricity starts flowing

The meter is installed when the customer’s electrician informs the utility that it can be installed (not at the same time as the connection). The installation is done by the utility’s subsidiary (Mitox Oy) that is specialized in metering services. Customer does not need to contact this company separately, it is taken care of by the utility. Electricity starts flowing once meter is installed, and Mitox Oy has informed the utility that the meter has been installed.
Agency: Helen Electricity Network
7 calendar days no charge