Ghana

Dealing with Construction Permits in

Ghana

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: GHS 468,027
  • City: Accra

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Submit application for permit from the Land Commission

Before the approval process commences at the Town and Country Planning Department (TCPD), the department must confirm that the land where the warehouse is to be located belongs to the applicant. To do so, the TCPD will provide the applicant with a letter to be submitted to the Land Title Registry/Land Commission along with the applicant’s site plan. The TCPD requires stamps from the Land Commission on its documents to prevent applicants from bringing in forged or outdated documents.

Agency: Land Commission
90 days no charge
2 Apply for building permit with the Town and Country Planning Department

The TCPD has been decentralized, so the local level in Accra is part of the Accra Metropolitan Assembly (AMA). So, to start the approval process for the building permit, a technical committee is set up by the TCPD, including other officials within the AMA. After the technical examination, a recommendation is made to the Statutory Planning Committee (SPC). The SPC is an intergovernmental committee made up of officials from the TCPD, the Environmental Protection Agency, the Survey Department, the Fire Service, and utility companies who meet periodically to approve building permits. They are required by law to have reviewed the application within 3 months after it is submitted and to inform the applicant of their decision. Survey respondents note that, without following up on the application, hearing from the committee within 3 months is unlikely. However, applicants have the right to commence building if they have not heard anything from the committee after 3 months. In practice, many people go ahead and build without waiting for the permit.

Agency: Town and Country Planning Department
90 days USD 1,909
* 3 Obtain approval of planning scheme


1 day GHS 100
* 4 Obtain approval of architectural and engineering design

The approval is issued by the Architectural/Engineering Department of the Accra Metropolitan Authority.

Agency: Accra Metropolitan Authority (Architectural/ Engineering Department)
1 day USD 3,600
* 5 Obtain opinion of the public health authority



Agency: Public Health Authority
1 day GHS 100
* 6 Obtain fire protection opinion



Agency: Fire Department
1 day GHS 100
7 Receive inspection after foundation has been laid

Inspections are to be carried out by the building inspectors at the end of each phase of the building: foundation, floor level, lintel, roofing, and finishing. Special coupons are provided when the building permit is granted, and the builder is supposed to send the appropriate coupon to the authorities informing them of the completion of that phase so that an inspection can be conducted. In practice this is rarely done.

Agency: Building Inspectorate
1 day no charge
8 Receive inspection after floor level has been finished

Inspections are to be carried out by the building inspectors at the end of each phase of the building: foundation, floor level, lintel, roofing, and finishing. Special coupons are provided when the building permit is granted, and the builder is supposed to send the appropriate coupon to the authorities informing them of the completion of that phase so that an inspection can be conducted. In practice this is rarely done. However, building inspectors are regularly sent to inspect buildings under construction.

Agency: Building Inspectorate
1 day no charge
9 Receive inspection after lintel has been finished

Inspections are to be carried out by the building inspectors at the end of each phase of the building: foundation, floor level, lintel, roofing, and finishing. Special coupons are provided when the building permit is granted, and the builder is supposed to send the appropriate coupon to the authorities informing them of the completion of that phase so that an inspection can be conducted. In practice this is rarely done. However, building inspectors are regularly sent out to inspect buildings under construction.

Agency: Building Inspectorate
1 day no charge
10 Receive inspection after roofing has been finished

Inspections are to be carried out by the building inspectors at the end of each phase of the building: foundation, floor level, lintel, roofing, and finishing. Special coupons are provided when the building permit is granted, and the builder is supposed to send the appropriate coupon to the authorities informing them of the completion of that phase so that an inspection can be conducted. In practice this is rarely done. However, building inspectors are regularly sent out to inspect buildings under construction.

Agency: Building Inspectorate
1 day no charge
* 11 Receive an inspection at the end of the construction

Inspections are to be carried out by the building inspectors at the end of each phase of the building: foundation, floor level, lintel, roofing, and finishing. Special coupons are provided when the building permit is granted, and the builder is supposed to send the appropriate coupon to the authorities informing them of the completion of that phase so that an inspection can be conducted. In practice this is rarely done. However, building inspectors are regularly sent out to inspect buildings under construction.

Agency: Building Inspectorate
30 days GHS 600
* 12 Obtain feasibility study from water and sewage

Obtaining a feasibility study from water and sewage happens after construction starts.

Agency: Ghana Water Company Ltd.
30 days GHS 1,000
* 13 Obtain water and sewage connection



Agency: Ghana Water Company Ltd.
1 day no charge
* 14 Obtain feasibility study from telephone company

Obtaining a feasibility study from the telephone company happens after construction starts.

Agency: Ghana Telecom
30 days GHS 200
* 15 Obtain telephone connection



Agency: Ghana Telecom
1 day no charge
16 Submit As-Built Drawings to Accra Metropolitan Assembly

The typical construction project in Ghana involves three entities: the owner, the contractor, and the consultant for the project (who provides supervision on behalf of the owner). Since the case considered here assumes that the owner and the contractor are the same entity, there is no reason for the consultant to be taken into account. The consultant performs all the inspections during construction. Therefore, those inspections are not included here. On completion of the project, the contractor prepares as-built drawings and forwards them to the AMA and the owner. The consultants for the project approve the project as meeting specifications and issue the completion certificate.

Agency: Accra Metropolitan Authority
1 day no charge
* Takes place simultaneously with another procedure.