Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: GNF 2,080,960,000
  • City: Conakry

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain cadastre extract



Agency: Cadastre
7 days GNF 150,000
2 Legalize copy of property title



Agency: Legal Clerk, Notary, or Huissier de Justice
2 days GNF 50,000
3 Obtain geological and geotechnical survey



Agency: BGGA
10 days GNF 650,000
4 Obtain building permit

The application is addressed to the Ministry of Urban Planning and Housing. The dossier contains the following documents:
- request to the Minister, Ministre de l'Urbanisme, to the Governor of the city or to the Mayor- Maire de la Commune according to the building use and the location;
- Property title (Titre Foncier, Décrêt, Arrêté ou Bail)
- Architectural and technical plans (Structure, Installations électriques and hydrosanitaires); the descrptive document of the project prepared by an architect office, and the soil analysis.

If BuildCo does not follow up on the application, the building permit will not be granted. A person within BuildCo needs to be assigned to follow up on the application daily.

Agency: Direction Nationale de L’Habitat et de la Construction
180 days GNF 5,000,000
5 Receive on-site inspection from the Technical Department of Architecture and Urban Planning (Département Technique d’Architecture et de l’Urbanisme) upon commencement of construction



Agency: Technical Department of Architecture and Urban Planning (Département Technique d’Architecture et de l’Urbanisme)
1 day no charge
6 Receive on-site inspection from the Department of Architecture and Construction (Département d’Architecture et de Construction) upon commencement of construction



Agency: Department of Architecture and Construction (Département d’Architecture et de Construction)
1 day no charge
7 Receive on-site inspection from the Town Taxes Service (Service des Impots de la Commune)

The municipal tax authority (Service des Impots de la Commune) inspects the site to ensure that BuildCo is paying withholding taxes on worker salaries.

Agency: Service des Impots de la Commune
1 day no charge
8 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. The agency may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
9 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
10 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
11 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
12 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
13 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
14 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
15 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
16 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
17 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
18 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
19 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
20 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
21 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
22 Receive on-site inspection from the local service for salubrity (service de salubrité)

The local health agency (service de salubrité) inspects the site every 2 weeks. It may visit as often as every week depending on the project.

Agency: Local Service for Salubrity (service de salubrité)
1 day no charge
23 Pay real estate tax

Real estate taxes and the occupancy tax (tax à l' occupation) of GNF 450,000 (paid only once) must be paid after construction is finished.

Agency: Town Taxes Service (Service des Impots de la Commune)
1 day GNF 450,000
24 Request water connection



Agency: Guinea Water Company (SEG)
1 day no charge
25 Receive inspection by water company



Agency: Guinea Water Company (SEG)
1 day no charge
26 Obtain water connection



Agency: Guinea Water Company (SEG)
36 days GNF 250,000
* 27 Request phone line



Agency: SOTELGUI SA.
1 day no charge
28 Receive onsite inspection for cost estimate by phone company



Agency: SOTELGUI SA.
3 days GNF 218,000
29 Obtain phone line



Agency: SOTELGUI SA.
28 days no charge
* Takes place simultaneously with another procedure.