Hungary

Dealing with Construction Permits in

Hungary

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: HUF 143,066,000
  • City: Budapest

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Request and obtain certificate of site ownership and site map from the Földhivatal

The site map is obtained by BuildCo. The site ownership certificate can be obtained either by BuildCo or by the local construction authority. The authorities have been introduced electronic application and database, and internal administrative process has become more efficient and takes 1 day to complete.

Agency: Földhivatal
1 day HUF 10,000
2 Request and obtain construction license

Hungary passed a new Building regulation in October 2009 that reduced the legal time to issue a building permit from 60 to 45 days.

Agency: Municipality
45 days HUF 10,000
* 3 Received on-site inspection

There is no need to request the inspection. After the permit is obtained, the local construction authority decides when it will conduct the inspection. In general, for smaller scale projects, the inspection may never even take place.

Agency: Municipality
1 day no charge
* 4 Request and obtain the construction authority approval on the architectural and technical plans, and technical description

The construction authority approves the plans and descriptions. Although there is a time limit of 30 days, a lack of response is not to be construed as approval. As a rule, it takes 45 days to complete the procedure.

Agency: Municipality
45 days no charge
* 5 Received on-site inspection from the construction authority

The inspection may take place anytime during the construction cycle. There is no need to request it.

Agency: Municipality
1 day no charge
* 6 Request an authorization from the water authorities

A written authorization from the water utility must be obtained. The authorization must be obtained before the building permit is issued, but it can be processed simultaneously with the building permit.

Agency: Budapest Water Company
1 day no charge
* 7 Receive inspection from water authorities



Agency: Budapest Water Company
1 day no charge
* 8 Obtain an authorization from the water authorities



Agency: Budapest Water Company
29 days no charge
* 9 Request an authorization from electricity works

A written authorization from the electricity utility must be obtained. The authorization must be obtained before the building permit is issued, but it can be processed simultaneously with the building permit.

Agency: Budapesti Elektromos Művek Rt.
1 day no charge
* 10 Receive inspection from electricity authorities



Agency: Budapesti Elektromos Művek Rt.
1 day no charge
* 11 Obtain authorization from electricity authorities



Agency: Budapesti Elektromos Művek Rt.
29 days no charge
* 12 Request an authorization from sewage authorities

A written authorization from the sewerage utility must be obtained. The authorization must be obtained before the building permit is issued, but it can be processed simultaneously with the building permit.

Agency: Sewage Works
1 day no charge
* 13 Receive inspection from sewage authorities



Agency: Sewage Works
1 day no charge
* 14 Obtain authorization from sewage authorities



Agency: Sewage Works
29 days no charge
* 15 Request and obtain fire protection authorization

The architectural plans contain the fire protection statement, which must be approved by the Fire Department. The authorization must be obtained before the building permit is issued, but it can be processed simultaneously with the building permit.

Agency: Fire Authority
30 days no charge
* 16 Obtain Statement of the Municipal Planning Committee

If the Municipal Planning Committee characterizes the location of the new building as “special” and finds other characteristics, such as size and color, to be exceptions to local regulations, a statement must be obtained from the committee. The documents to be filed are the Land Registry Office ownership title and site map.
The Municipal Planning Committee now has a stronger mandate and role in handling this procedure. (In the past, its role was advisory in nature).

Agency: Municipal Planning Committee
30 days no charge
* 17 Provide evidence of the availability of a licensed site manager and notify about construction inception

The builder is required to submit all documents 15 days prior to the start of the construction. The public works authority may require the investor to pay a regular fee to the public network (e.g., sewerage) to cover operational costs. The construction authority may conduct an inspection at any stage.

If the value of any construction project exceeds HUF 30 million, BuildCo must notify the County Government Office of its intention to start construction. The Regional Administrative Office must either approve or disapprove the start of construction. The office has authority over the participants, their liability, the building permit, the state of the neighboring buildings (which must be documented), and provides information to the tax authority (to curb unauthorized activity) and to the local authority.

Agency: County Government Office
5 days no charge
* 18 Request and obtain Letter from Tax Authority

Beginning in 2005, data reporting to the Tax Authority is required for all construction projects valued at more than HUF 10 million. The builder submits a letter to the Tax Authority along with the application for a building permit.
If the value of the construction project is above HUF 10 million, the local authority informs the following institutions:
- Tax Authority.
- Construction Authority (for quality control).
- Labor Authority (to control the informal economy).

Agency: Tax Authority
30 days no charge
19 Request and receive connection to the sewerage network



Agency: Sewage Works
21 days no charge
* 20 Contact a registered technician to set up sewerage system



Agency: Registered Technician
1 day no charge
* 21 Request and receive connection to telephone

There are several network providers besides Hungarian Telephone and Cable Corp. There is a competition on this market, so it is recommended to obtain offers from several network providers. Costs therefore could vary between 15,000 and 100,000 HUF

Agency: Hungarian Telephone and Cable Corp.
14 days HUF 30,000
* 22 Request water connection

The water connection consists of two parts: the on-site part (which must be done by a registered technician) and the off-site part (which is the connection from the existing utility to the on-site part). The builder must contact the people in charge of each part separately.

The cost depends on the position of the building (distance from the source, local situation). Costs are specific to each case, depending on the expenditures involved.

Agency: Budapest Water Company
1 day HUF 100,000
* 23 Contact a registered technician to set up water connection



Agency: Registered Technician
1 day no charge
* 24 Receive on-site inspection to check on cleanness for water connection

The inspection is requested when the connection is requested.

Agency: Budapest Water Company
1 day no charge
* 25 Receive connection to water



Agency: Budapest Water Company
10 days no charge
26 Notify authorities of the completion of construction

When the building is completed and the municipality has been notified, the builder (owner) must arrange for a site inspection by the municipal experts; water, electricity, and sewerage providers; and the Fire Department. After the on-site inspection, all the inspectors must declare that the building has been completed in compliance with the technical plans or identify any unfinished work. If there is unfinished work, the deadline for completion must be stated in a document. After completion, the authority issues the occupancy permit.

Agency: Municipality
1 day no charge
27 Receive final inspection of the completed building



Agency: Municipality
1 day no charge
* 28 Obtain Occupancy Permit

When the building is completed and the municipality has been notified, the builder (owner) must arrange for a site inspection by the municipal experts; water, electricity, and sewerage providers; and the Fire Department. After the on-site inspection, all the inspectors must declare that the building has been completed in compliance with the technical plans or identify any unfinished work. If there is unfinished work, the deadline for completion must be stated in a document. After completion, the authority issues the occupancy permit.

Agency: Municipality
30 days no charge
* 29 Register the building with the Land Registry Office

The owner must submit a “realization plan” to the Land Registry Office to register the new building and the owner’s name on the official site map. In small villages, registration takes 30 days; in big cities and especially in the capital, registration might take from 30 days to 4 years, depending on the specifications of the lot. There is no registration fee, but there is the cost of a lawyer’s services (HUF 15,000), although the company’s own lawyer may handle the process.

Agency: Land Registry Office
30 days no charge
* Takes place simultaneously with another procedure.