Dealing with Construction Permits
Info
Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.
| Indicator |
Denpasar |
East Asia & Pacific |
OECD |
The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. View methodology
Procedures (number)
|
12 |
17 |
14 |
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. View methodology
Time (days)
|
94 |
148 |
143 |
Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. View methodology
Cost (% of income per capita)
|
71.4 |
86.9 |
78.7 |
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Obtain Letter of Introduction (Surat Penyanding) from Head of Sub-district
|
3 days
|
No cost
|
| 2 |
Obtain statement of land dispute from Local Office of National Land Board (BPN)
|
3 days
|
No cost
|
| 3 |
Request building permit (Package Permit: IMB and PPM) from Licensing Agency (Dinas Perizinan)
|
1 day
|
No cost
|
| 4 |
Make payment for Building Construction Permit (IMB) at Bank Pembangunan Daerah (BPD)
|
1 day
|
IDR 12,310,670 (Cost of construction permit + Border Administrator Service Duty; the Principal Construction Permit is free of cost)
|
| 5 |
Obtain building permit (Package Permit: IMB and PPM) from Licensing Agency (Dinas Perizinan)
|
11 days
|
No cost
|
| 6 |
Notify City Planning and Housing Agency (Dinas Tata Ruang dan Perumahan) about progress of the construction
|
1 day
|
No cost
|
| 7 |
Receive an inspection from City Planning and Housing Agency (Dinas Tata Ruang dan Perumahan)
|
1 day
|
No cost
|
| 8 |
Obtain Environmental Management Plan and Environmental Monitoring Plan (UKL/UPL) approval from local Environmental Agency
|
21 days
|
No cost
|
| 9 |
Register with Local Tax Office (Kantor Pajak Pratama, KPP)
|
25 days
|
No cost
|
| 10 |
Register the warehouse (Package Permit: TDG, SITU, HO) with the Licensing Agency (Dinas Perizinan)
|
12 days
|
IDR 100,000 (Cost for a warehouse with an area between 36 and 2500 square meters)
|
| * 11 |
Request and connect to water and sewage with PDAM
|
1 day
|
IDR 6,255,700
|
| * 12 |
Request and connect to telephone with PT Telekomunikasi Indonesia Tbk (Telkom)
|
25 days
|
IDR 500,000
|
* Takes place simultaneously with another procedure.