This page summarizes Subnational Doing Business in Indonesia 2012 data for Jakarta. The first table shows its rank among 20 cities/regions in Indonesia. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.

Economy Overview

Region East Asia & Pacific
Income Category Lower middle income
Population 246,864,191
GNI Per Capita (US$) 3,420.00
Ease of Doing Business Rank among 20 cities in Indonesia Top city in Indonesia
n.a. n.a.
Topic Rankings Rank among 20 cities in Indonesia Top city in Indonesia
Starting a Business 8 Yogyakarta
Dealing with Construction Permits 19 Balikpapan
Registering Property 1 Bandung, Jakarta

Subnational Data


Dealing with Construction Permits

Info

Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.

Indicator Jakarta East Asia & Pacific OECD

The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties.

View methodology
Procedures (number)
13 16 13

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.

View methodology
Time (days)
158.0 146.0 147.1

Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded.

View methodology
Cost (% of income per capita)
105.3 104.7 84.1
No. Procedure Time to Complete Associated Costs
1 Request Pre-approval letter from Zoning Department 1 day IDR 1,482,000
2 Receive inspection from Zoning Department 1 day No cost
3 Obtain Pre-approval letter from Zoning Department 20 days No cost
* 4 Request and obtain notarized copy of Land Ownership certificate 1 day IDR 25,000
5 Request and obtain the preparation of the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL) 8 days IDR 15,000,000
6 Request and obtain the approval for the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL) 10 days No cost
7 Request and obtain Building Construction Permit (IMB) 21 days IDR 9,104,200
8 Request and obtain building completion and compliance minutes 28 days IDR 62,500
9 Obtain building usage permit (IPB) 49 days No cost
10 Register with Land and Building Tax Office 11 days No cost
11 Register the warehouse with the regional office of the Ministry of Industry and Trade 9 days IDR 100,000
* 12 Obtain water and sewerage connection 8 days IDR 2,000,000
* 13 Obtain phone connection 4 days IDR 500,000
* Takes place simultaneously with another procedure.