Ease of Doing Business in
Jakarta - Indonesia
This page summarizes Doing Business data for Jakarta. The first table shows its rank among 20 cities/regions in Indonesia. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.
Economy Overview
| Region |
East Asia & Pacific |
| Income Category |
Lower middle income |
| Population |
242,325,638 |
| GNI Per Capita (US$) |
2,940.00 |
|
Ease of Doing Business Rank among 20 cities in Indonesia
|
Top city in Indonesia |
| n.a. |
n.a. |
Subnational Data
Dealing with Construction Permits
Info
Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.
| Indicator |
Jakarta |
East Asia & Pacific |
OECD |
The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. View methodology
Procedures (number)
|
13 |
17 |
14 |
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. View methodology
Time (days)
|
158 |
148 |
143 |
Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. View methodology
Cost (% of income per capita)
|
105.3 |
86.9 |
78.7 |
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Request Pre-approval letter from Zoning Department
|
1 day
|
IDR 1,482,000
|
| 2 |
Receive inspection from Zoning Department
|
1 day
|
No cost
|
| 3 |
Obtain Pre-approval letter from Zoning Department
|
20 days
|
No cost
|
| * 4 |
Request and obtain notarized copy of Land Ownership certificate
|
1 day
|
IDR 25,000
|
| 5 |
Request and obtain the preparation of the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)
|
8 days
|
IDR 15,000,000
|
| 6 |
Request and obtain the approval for the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)
|
10 days
|
No cost
|
| 7 |
Request and obtain Building Construction Permit (IMB)
|
21 days
|
IDR 9,104,200
|
| 8 |
Request and obtain building completion and compliance minutes
|
28 days
|
IDR 62,500
|
| 9 |
Obtain building usage permit (IPB)
|
49 days
|
No cost
|
| 10 |
Register with Land and Building Tax Office
|
11 days
|
No cost
|
| 11 |
Register the warehouse with the regional office of the Ministry of Industry and Trade
|
9 days
|
IDR 100,000
|
| * 12 |
Obtain water and sewerage connection
|
8 days
|
IDR 2,000,000
|
| * 13 |
Obtain phone connection
|
4 days
|
IDR 500,000
|
* Takes place simultaneously with another procedure.