This page summarizes Doing Business data for Surabaya. The first table shows its rank among 20 cities/regions in Indonesia. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.

Economy Overview

Region East Asia & Pacific
Income Category Lower middle income
Population 242,325,638
GNI Per Capita (US$) 2,940.00
Ease of Doing Business Rank among 20 cities in Indonesia Top city in Indonesia
n.a. n.a.
Topic Rankings Rank among 20 cities in Indonesia Top city in Indonesia
Starting a Business 14 Yogyakarta
Dealing with Construction Permits 16 Balikpapan
Registering Property 11 Jakarta

Subnational Data


Dealing with Construction Permits

Info

Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.

Indicator Surabaya East Asia & Pacific OECD

The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties.

View methodology
Procedures (number)
11 17 14

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.

View methodology
Time (days)
116 148 143

Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded.

View methodology
Cost (% of income per capita)
71.2 86.9 78.7
No. Procedure Time to Complete Associated Costs
1 Notarize copy of Land Certificate at Notary Office 3 days IDR 50,000
2 Request City Planning Statement (SKRK) at Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 1 day No cost
3 Receive inspection from City Planning Agency (Dinas Cipta Karya dan Tata Ruang) 1 day No cost
4 Obtain City Planning Statement (SKRK) from Surabaya one-stop shop (UPTSA) 28 days IDR 2,822,000 [(0.01 x Plot area x Taxation value x Location Index) + administrative costs of IDR 35.000]
5 Obtain Environmental Monitoring Plan and Environmental Management Plan (UKL/UPL) approval from local Environmental Control Agency (BLH) 1 day No cost
6 Obtain Building Construction Permit (IMB) from Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 30 days IDR 14,225,800
7 Obtain official report on completion of construction and compliance with building permit from City Planning Agency (Dinas Cipta Karya dan Tata Ruang) 28 days IDR 62,500
8 Register warehouse with Local Revenue Agency (Dispenda) 2 days No cost
9 Register the warehouse with Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 1 day No cost
* 10 Request and connect to water and sewage with PDAM 21 days IDR 1,500,000
* 11 Request and connect to telephone with PT Telekomunikasi Indonesia Tbk (Telkom) 2 days IDR 450,000
* Takes place simultaneously with another procedure.