This page summarizes Doing Business data for Surabaya. The first table shows its rank among 20 cities/regions in Indonesia. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.
Economy Overview
| Region |
East Asia & Pacific |
| Income Category |
Lower middle income |
| Population |
242,325,638 |
| GNI Per Capita (US$) |
2,940.00 |
|
Ease of Doing Business Rank among 20 cities in Indonesia
|
Top city in Indonesia |
| n.a. |
n.a. |
Subnational Data
Dealing with Construction Permits
Info
Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.
| Indicator |
Surabaya |
East Asia & Pacific |
OECD |
The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. View methodology
Procedures (number)
|
11 |
17 |
14 |
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. View methodology
Time (days)
|
116 |
148 |
143 |
Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. View methodology
Cost (% of income per capita)
|
71.2 |
86.9 |
78.7 |
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Notarize copy of Land Certificate at Notary Office
|
3 days
|
IDR 50,000
|
| 2 |
Request City Planning Statement (SKRK) at Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap)
|
1 day
|
No cost
|
| 3 |
Receive inspection from City Planning Agency (Dinas Cipta Karya dan Tata Ruang)
|
1 day
|
No cost
|
| 4 |
Obtain City Planning Statement (SKRK) from Surabaya one-stop shop (UPTSA)
|
28 days
|
IDR 2,822,000 [(0.01 x Plot area x Taxation value x Location Index) + administrative costs of IDR 35.000]
|
| 5 |
Obtain Environmental Monitoring Plan and Environmental Management Plan (UKL/UPL) approval from local Environmental Control Agency (BLH)
|
1 day
|
No cost
|
| 6 |
Obtain Building Construction Permit (IMB) from Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap)
|
30 days
|
IDR 14,225,800
|
| 7 |
Obtain official report on completion of construction and compliance with building permit from City Planning Agency (Dinas Cipta Karya dan Tata Ruang)
|
28 days
|
IDR 62,500
|
| 8 |
Register warehouse with Local Revenue Agency (Dispenda)
|
2 days
|
No cost
|
| 9 |
Register the warehouse with Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap)
|
1 day
|
No cost
|
| * 10 |
Request and connect to water and sewage with PDAM
|
21 days
|
IDR 1,500,000
|
| * 11 |
Request and connect to telephone with PT Telekomunikasi Indonesia Tbk (Telkom)
|
2 days
|
IDR 450,000
|
* Takes place simultaneously with another procedure.