Indonesia

Ease of Doing Business in

Surabaya - Indonesia

This page summarizes Subnational Doing Business in Indonesia 2012 data for Surabaya. The first table shows its rank among 20 cities/regions in Indonesia. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.

Economy Overview

Region East Asia & Pacific
Income Category Lower middle income
Population 246,864,191
GNI Per Capita (US$) 3,420.00
Ease of Doing Business Rank among 20 cities in Indonesia Top city in Indonesia
n.a. n.a.
Topic Rankings Rank among 20 cities in Indonesia Top city in Indonesia
Starting a Business 14 Yogyakarta
Dealing with Construction Permits 16 Balikpapan
Registering Property 11 Bandung, Jakarta

Subnational Data


Dealing with Construction Permits

Info

Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.

Indicator Surabaya East Asia & Pacific OECD

The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties.

View methodology
Procedures (number)
11 16 13

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.

View methodology
Time (days)
116.0 146.0 147.1

Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded.

View methodology
Cost (% of income per capita)
71.2 104.7 84.1
No. Procedure Time to Complete Associated Costs
1 Notarize copy of Land Certificate at Notary Office 3 days IDR 50,000
2 Request City Planning Statement (SKRK) at Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 1 day No cost
3 Receive inspection from City Planning Agency (Dinas Cipta Karya dan Tata Ruang) 1 day No cost
4 Obtain City Planning Statement (SKRK) from Surabaya one-stop shop (UPTSA) 28 days IDR 2,822,000 [(0.01 x Plot area x Taxation value x Location Index) + administrative costs of IDR 35.000]
5 Obtain Environmental Monitoring Plan and Environmental Management Plan (UKL/UPL) approval from local Environmental Control Agency (BLH) 1 day No cost
6 Obtain Building Construction Permit (IMB) from Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 30 days IDR 14,225,800
7 Obtain official report on completion of construction and compliance with building permit from City Planning Agency (Dinas Cipta Karya dan Tata Ruang) 28 days IDR 62,500
8 Register warehouse with Local Revenue Agency (Dispenda) 2 days No cost
9 Register the warehouse with Surabaya one-stop shop (Unit Pelayanan Terpadu Satu Atap) 1 day No cost
* 10 Request and connect to water and sewage with PDAM 21 days IDR 1,500,000
* 11 Request and connect to telephone with PT Telekomunikasi Indonesia Tbk (Telkom) 2 days IDR 450,000
* Takes place simultaneously with another procedure.