Jamaica

Dealing with Construction Permits in

Jamaica

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: JMD 46,200,000
  • City: Kingston

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain approval of building plans by KSAC

BuildCo must obtain approval of building plans from the Planning Authority, the Fire Department, the National Environmental Protection Agency (NEPA), and other authorities concerned. Several documents are required to obtain this approval, including property title and proof of ownership. Approval is valid for 2 years and can be renewed.

To obtain approval, BuildCo files the drawings with the municipality. Four meetings are held to review the drawings:
- Fire.
- Health.
- Road.
- A general meeting after all others are completed and NEPA approval is received.
Each meeting has a set date, normally one a week sequentially. If there is a holiday, the meeting will be postponed. If BuildCo misses a meeting, the whole process will be prolonged. In November 2007 the government of Jamaica created an initiative to reduce the number of days to obtain a permit from 210 to 90 days. It is expected that by the end of 2008 this will be part of a new building law that includes the creation of a "one stop shop". Currently, on average, the time to obtain a license have been reduce to 130 days.

Agency: Municipal Authority(KSAC) Kingston & St. Andrew corporation
130 days JMD 924,000
* 2 Obtain approval from Environmental Protection Agency

Meanwhile, BuildCo files the same document with the NEPA for approval of the plans. In simple cases, approval takes 10 workings days. In complicated cases, an environmental impact assessment is required, and approval might take much longer. BuildCo files NEPA's approval with the municipality.

Agency: Environmental Protection Agency
14 days no charge
3 Request and receive excavation inspection from KSAC

BuildCo sends a written notification enclosed with the project approval number to the building authority 3 days in advance of the excavation inspection. If the inspector comes on schedule, the construction does not have to stop.

Agency: Municipal Authority(KSAC) Kingston & St. Andrew corporation
1 day no charge
4 Request and receive foundation steel inspection from KSAC



Agency: Municipal Authority(KSAC) Kingston & St. Andrew corporation
1 day no charge
5 Request and receive beam and roof inspection



Agency: Municipal Authority(KSAC) Kingston & St. Andrew corporation
1 day no charge
6 Obtain sewage installation



Agency: National Water Commission
12 days JMD 10,000
* 7 Obtain telephone connection



Agency: Cable and Wireless Jamaica Ltd.
7 days JMD 1,000
* 8 Obtain water connection



Agency: National Water Commission
5 days JMD 45,000
* Takes place simultaneously with another procedure.