Kosovo

Dealing with Construction Permits in

Kosovo

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: EUR 700,000
  • City: Pristina

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Request and obtain the property certificate and a copy of land plot plan from the municipal Geodesy and Cadastral Directorate

Copies are valid for 180 days and will be required for the building permit application.

Agency: Municipality: Geodesy and Cadastral Directorate
2 days EUR 8
2 Request and obtain approval of compliance with technical and urbanistic requirements

Authorities verify if the building can be constructed in the specific area and compliance of the building's design with the urban plan. In addition, the authorities will analyze the building plans to assess the compliance with security and technical construction norms.

Agency: Municipality: Urban and Technical Commission
30 days EUR 10
3 Request and obtain validation of the main project

Directorate verifies the main project plan and assess the amount of fees that need to be paid in order to obtain the building permit.

Agency: Municipality: Technical Audit Directorate
5 days no charge
4 Request and obtain initial clearance from the electricity authority (KEK)

Present electrical plans for assessment of compliance with safety norms.

Agency: KEK (Korporata Energjetike e Kosovës)
2 days EUR 10
5 Request and obtain fire protection clearance

Present emergency plans in case of fire for assessment of compliance with safety norms.

Agency: Ministry of Internal Affairs, Emergency Department
15 days EUR 50
6 Request and obtain initial clearance from water authority (Ujësjellësi Rajonal e Kosovës)

Present water plans for assessment of compliance with safety norms.

Agency: Ujësjellësi Rajonal e Kosovës
2 days no charge
7 Pay Municipal fees for the building permit at a commercial bank



Agency: Commercial bank
1 day EUR 13,007
8 Request and obtain the building permit from the Planning, Urbanism and Construction Directorate of the Municipality

Applicant presents the receipt and requests the building permit. Usually, applicants will have to wait between 20 to 35 days in order to receive the building permit.

Agency: Municipality: Planning, Urbanism and Construction Directorate
30 days no charge
9 Notify to the Planning, Urbanism and Construction Directorate of the Municipality about the start of construction work

The notification needs to be submitted 8 days before the beginning of construction. The Technical Commission may visit the site on an unannounced basis to verify whether the construction is in accordance with the plan. Due to the volume of construction in Pristina, such visits are rare.

Agency: Planning, Urbanism and Construction Directorate of the Municipality
1 day no charge
10 Receive on-site inspection by the Municipal Technical Commission



Agency: Planning, Urbanism and Construction Directorate of the Municipality
1 day no charge
11 Request and connect to water and sewage services



Agency: Ujësjellësi Rajonal e Kosovës
7 days EUR 181
* 12 Request and connect to telecommunications services



Agency: Telecommunications Authority (Posta dhe Telekomunikacioni i Kosovës)
5 days EUR 31
13 Request technical approval of the building by the Municipal Technical Commission



Agency: Municipality: Technical Commission
1 day EUR 30
14 Receive technical approval of the building by the Municipal Technical Commission and obtain usage permit



Agency: Municipality: Technical Commission
39 days EUR 10
15 Register property at the Geodesy and Cadastral Directorate of the Municipality



Agency: Geodesy and Cadastral Directorate of the Municipality
165 days no charge
* 16 Pay registration fee at a commercial bank



Agency: Commercial Bank
1 day EUR 5,203
* 17 Receive inspection from the Geodesy and Cadastral Directorate of the Municipality



Agency: Geodesy and Cadastral Directorate of the Municipality
1 day no charge
* Takes place simultaneously with another procedure.