Kosovo

Getting Electricity in

Kosovo

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Kosovo.

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Kosovo to 185 other economies.

  • Standardized Company

  • Name of Utility: Kosovo Energy Corporation (KEK)
  • City: Pristina
No. Procedure Time to Complete Associated Costs
1 Apply for electricity connection at KEK (Korporata Energjetike e Kosovës) and await “energy agreement”/technical guidelines

Applicants should apply in person. The forms are available on-line. The following documents should be attached to the application: electrical plan, construction permit, receipts stating the origin of materials. They will also need to explain the load requirements and justify the need for the requested load.

After the visit (see procedure below), the staff from KEK will prepare the “energy agreement”. This document explains the required next steps and provides connection works’ guidelines for the electrical contractor. The electrical contractor will lead the works under KEK’s supervision. Applicants have to wait on average 1 week after the external inspection to receive the energy agreement.

Applicant pays the EUR 500 fee (fees for “processing technical documentation”). Applicants have 4 days to modify the energy agreement.
Agency: KEK
14 calendar days EUR 3,300.0
* 2 Receive an external inspection from KEK

Inspector visits the property and assesses connection costs. Applicants have to wait on average a week after they submit the application. Someone from the applicant’s party has to be present during the inspection.
Agency: KEK
7 calendar days no charge
3 Obtain an excavation permit at the Municipality

Usually KEK obtains an excavation permit but if it is a big customer like the load assumed in the case study the customer obtains an excavation permit.
Agency: Muncipality
3 calendar days no charge
4 Await completion of the external connection works by a private electrical contractor

The electrical contractor purchases required materials for the connection which takes 1-3 weeks. All the connection related works will be performed by the electrical contractor under the supervision of KEK. The meter will be provided by KEK. The works take 2 to 4 weeks. Installation of a substation transformer is required.
Agency: Electrical Contractor
24 calendar days EUR 21,000.0
* 5 Inspection of the works and purchased equipment by the utility

KEK will conduct two inspections of the works once the electrical contractor is half way through with works and at the end. At the same time after materials for the external connection have been purchased KEK will verify the authenticity of the materials at this inspection.
Agency: KEK
2 calendar days no charge
6 Inspection of the completed works by the utility and sign supply contract

After the works are completed three teams are sent by KEK for the final inspection. One team inspects the external works, one team inspects internal wiring and the last team concludes the supply contract with the client.
Agency: KEK
2 calendar days no charge
7 KEK installs the meter and electricity starts flowing

After the inspection, the client receives an invoice for the connection fee, which can be paid at any commercial bank. Once receipt of payment is confirmed, KEK comes back to the site to install and seal the meter and electricity starts to flow.
Agency: KEK
3 calendar days no charge
* Takes place simultaneously with another procedure.

Explore Economy Data


- OR -