Kuwait

Dealing with Construction Permits in

Kuwait

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: KWD 277,000
  • City: Kuwait City

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain lot plan with site map from the Municipality of Kuwait



Agency: Municipality of Kuwait
3 days KWD 20
2 Obtain location clearances from the Municipal Authority



Agency: Municipality of Kuwait
1 day KWD 130
3 Obtain project clearance from the Ministry of Commerce and Industry



Agency: Ministry of Commerce and Industry
3 days KWD 20
4 Obtain zoning approval from the Municipal Authority

Builders request a lot plan as well as a zoning approval physically at the municipality. In fact, to obtain a copy of the lot plan a copy of the government’s lease agreement need to be taken to the municipality.

Agency: Municipality of Kuwait
8 days KWD 20
5 Submit building permit application to the Municipal Authority



Agency: Municipality of Kuwait
1 day KWD 100
6 Obtain telephone plan approval from the Ministry of Communications



Agency: Ministry of Communications
20 days KWD 1,500
* 7 Receive electricity inspection from Ministry of Electricity and Water



Agency: Ministry of Electricity and Water
1 day no charge
8 Obtain electricity plans approval from Ministry of Electricity and Water



Agency: Ministry of Electricity and Water
7 days KWD 4,000
* 9 Receive water inspection from Ministry of Electricity and Water



Agency: Ministry of Electricity and Water
1 day no charge
10 Obtain water plan approval from Ministry of Electricity and Water



Agency: Ministry of Electricity and Water
5 days KWD 3,000
* 11 Receive sewage inspection from Ministry of Public Works



Agency: Ministry of Public Works
1 day no charge
12 Obtain sewage plans approval from Ministry of Public Works



Agency: Ministry of Public Works
14 days KWD 2,000
13 Obtain building permit

BuildCo must submit Application Form 1 for a building license and attach the following documents (including the documents described in the procedures above): - A copy of the deed of title to the land, allocation decree, or lease agreement. In the case of an allocation decree or lease agreement, a recent rent receipt should be submitted. - A copy of the architectural contract between BuildCo and an accredited engineering firm responsible for the architecture of the building, - Original letter of zoning opinion. - Third-party liability insurance policy (covering 2 or 3 years, depending on the time required to complete the building). - Original copies of plans or blueprints of the building from the engineering firm, including all details of the external facade, internal design, internal and external diameters, calculation of building area and space area around the building. - Original soil test report. - Approval from the Safety Department. - Approval from the Roads Department, if underground parking is included (which does not apply to the warehouse project). - Form 2, Undertaking of compliance of the plans with the buildings codes and cadastres, which should be signed and submitted (by an engineering firm). - Form 3, Undertaking of compliance with the construction plans, which should be signed and submitted (by an engineering firm). - Undertaking to provide specific plans (done by an engineering firm) that meet the requirements of -- The Ministry of Electricity and Energy for the electric supply. -- The Ministry of Public Works for the sewerage system. -- The Public Authority for Civil Aviation for the height of the warehouse. -- The Ministry of Communications for the telephone lines.

Agency: Municipality of Kuwait
14 days KWD 150
14 Receive soil test inspection from the municipality

Several inspections may take place during construction. The following inspections are conducted by the municipality or by a local consulting engineer who submits the information to the municipality: soil inspection; excavation work inspection; foundation work inspection; steel work for slabs inspection; frame inspection; damp-proof course inspection; drainage inspection; timber scaffolding inspection; environmental inspection; inspection of the building’s surroundings; final inspection. The concrete work inspection and inspection of the structure are conducted by the Construction Board. The labor inspection is conducted by the Labor Inspection Agency from the Ministry of Social Affairs and Labor. The fire inspection is conducted by the Fire Department. All these inspections may take place. However, on average, the warehouse would undergo 3 to 4 inspections per year. Therefore, only three inspections are included here as procedures.

Agency: Municipality of Kuwait
1 day no charge
15 Receive mid-way through construction inspection from the municipality



Agency: Municipality of Kuwait
1 day no charge
16 Receive on-site inspection from municipality

The municipality inspects the buildings to ensure compliance with the drawings.

Agency: Municipality of Kuwait
1 day no charge
17 Obtain site take-over letter

BuildCo must submit an application for the site take-over letter and attach the following documents: - A copy of the construction license. - An undertaking from BuildCo that it shall carry out the construction work on the warehouse or, alternatively, that is has a construction contract with a contractor. In case of a construction contract with a contractor, a copy of the performance bond should be submitted. - An undertaking from an accredited supervising engineer to supervise the construction approved by the municipality. - Signature of the site take-over letter by BuildCo, the contractor (if any), and the municipality.
20 days KWD 10
18 Obtain telephone connection



Agency: Kuwait Telecom
17 days KWD 250
* 19 Obtain water connection



Agency: Kuwait Water Company
7 days KWD 750
* 20 Obtain sewage connection



Agency: Kuwait Water Company
7 days KWD 750
21 Prepare the file of cadastral measure of the structure


7 days KWD 10
22 Receive inspection from the fire department and obtain inspection certificate



Agency: Fire Department
1 day KWD 5
23 Obtain certificate of fire and panic safety form Civil Defense department



Agency: Civil Defense Department
5 days no charge
24 Register building with the real estate registry



Agency: Real Estate Registry
1 day KWD 10
* Takes place simultaneously with another procedure.