Malaysia

Getting Electricity in

Malaysia

Listed below are the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building.

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Name of Utility: Tenaga Nasional Berhad
  • City: Kuala Lumpur

About This Topic

To see indicator data for all economies, see the Getting Electricity page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Hire certified electrical engineer who provides certificate of compliance of internal wiring

This is a requirement while submitting application to utility.

Agency: Certified Electrical Engineer
1 calendar day MYR 650.0
2 Applicant submits application to Tenaga Nasional Berhad (TNB) via Electrical engineer, and awaits site visit

Submission shall be complete with all relevant documents and load data. Supply application form availaible at TNB offices (online applications are only available for domestic customers and housing delevopment projects). Documents to be attached are: site / location plan, electrical drawings, layout plan and identity card of owner. Douments to be attached include development plan approved by local authority, load profile & load details and premilinary metering scheme.

Agency: Tenaga Nasional Berhad
14 calendar days no charge
3 Receive site visit from TNB and await estimate

Once the utility engineer has visited the site, he submits the file for internal clearances, and then prepares the connection charge (estimate).

Agency: Tenaga Nasional Berhad
7 calendar days no charge
4 Customer receives estimates, makes payment of connection charges and security deposit, and TNB conducts external connection

Customer receives estimate and makes payment at the utility. Once payment is received, utility commences external connection works, after getting internal approvals and permits from local authorities. Security deposit is 2 months electricity usage, reimbursed at the time the account is terminated.

Agency: Tenaga Nasional Berhad
22 calendar days MYR 20,180.0
* 5 Electrical contractor purchases material and conducts external connection works

Some materials need to be purchased by customer (meter panel board, switchboard, cables, etc), which are related to the meter installation. This is available easily in local markets, and electrical contractor does the external connection.

Agency: Electrical Contractor
7 calendar days MYR 4,500.0
6 TNB installs meter and turns on electricity

Customer receives security deposit notice from TNB and makes payment of security deposit (reimbursed in third month bill). Customers submits Form G and H completed, electrical engineer's certificate of compliance of internal wiring (will need to provide this compliance certificate after all internal wiring is complete). TNB installs meter and turns on electricity.

Agency: Tenaga Nasional Berhad
7 calendar days no charge
* Takes place simultaneously with another procedure.