Micronesia, Fed. Sts.

Getting Electricity in

Micronesia, Fed. Sts.

Listed below are the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building.

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Name of Utility: Pohnpei Utilities Corporation (PUC)
  • City: Island of Pohnpei (Palikir/Kolonia)

About This Topic

To see indicator data for all economies, see the Getting Electricity page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 The client submits application and awaits estimate of connection fees from Pohnpei Utilities Corporation



Agency: Pohnpei Utilities Corporation
15 calendar days no charge
* 2 The client obtains external inspection by Pohnpei Utilities Corporation



Agency: Pohnpei Utilities Corporation
1 calendar day no charge
3 The client obtains external works, meter installation, and final connection by Pohnpei Utilities Corporation

The works consist of installing an overhead transformer. The material needed is usually not available in stock, and has to be imported by the utility. The client cannot buy the material themselves.

Agency: Pohnpei Utilities Corporation
60 calendar days USD 12,700.0
* Takes place simultaneously with another procedure.