Ease of Doing Business in
Grand Casablanca - Morocco
This page summarizes Doing Business data for Grand Casablanca. The first table shows its rank among 8 cities/regions in Morocco. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.
Economy Overview
| Region |
Middle East & North Africa |
| Income Category |
Lower middle income |
| Population |
32,272,974 |
| GNI Per Capita (US$) |
2,970.00 |
|
Ease of Doing Business Rank among 8 cities in Morocco
|
Top city in Morocco |
| 6 |
Souss-Massa-Draâ |
Subnational Data
Dealing with Construction Permits
Info
Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.
| Indicator |
Grand Casablanca |
Middle East & North Africa |
OECD |
The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. View methodology
Procedures (number)
|
19 |
17 |
14 |
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. View methodology
Time (days)
|
163 |
151 |
143 |
Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. View methodology
Cost (% of income per capita)
|
334.7 |
305.2 |
78.7 |
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Obtenir un plan cadastral et un plan de la situation
|
2 jours
|
MAD 60
|
| 2 |
Obtenir note de renseignements sur le terrain
|
9 jours
|
MAD 150
|
| 3 |
Déposer la demande et obtenir le permis de construire
|
20 jours
|
20 Dirhams / metre2 + 10 Dirhams (frais d'occupation de domaine publique) + 2 Dirhams /m2 (aux sapeurs pompiers); 50 dirhams pour les frais de timbre. (Dans ce cas, MAD 32 263,20 total)
|
| * 4 |
*Recevoir l'inspection des Autorités Municipales avant l'obtention du permis de construire
|
1 jour
|
sans frais
|
| 5 |
Recevoir l'inspection des Autorités Municipales pendant construction
|
1 jour
|
sans frais
|
| 6 |
Recevoir l'inspection des Autorités Municipales pendant construction
|
1 jour
|
sans frais
|
| 7 |
Recevoir l'inspection des Autorités Municipales pendant construction
|
1 jour
|
sans frais
|
| 8 |
Recevoir l'inspection des Autorités Municipales pendant construction
|
1 jour
|
sans frais
|
| 9 |
Recevoir l'inspection des Autorités Municipales pendant construction
|
1 jour
|
sans frais
|
| 10 |
Notifier les autorités municipales à l’achèvement des travaux et recevoir une dernière inspection
|
1 jour
|
sans frais
|
| 11 |
Obtenir le certificat de conformité
|
60 jours
|
sans frais
|
| 12 |
Demander l’autorisation pour se brancher au réseau d'eau potable et d'assainissement
|
1 jour
|
sans frais
|
| 13 |
Recevoir l'inspection de LYDEC
|
1 jour
|
sans frais
|
| 14 |
Obtenir le branchement au réseau d'eau potable et d’assainissement
|
57 jours
|
MAD 5 000
|
| * 15 |
*Demander l’autorisation de branchement du service d'électricité
|
1 jour
|
MAD 1 200 (1 000 pour le branchement et 200 pour les frais de timbre)
|
| * 16 |
*Recevoir contrôle sur place par LYDEC
|
1 jour
|
sans frais
|
| * 17 |
*Obtenir branchement au réseau d’électricité
|
12 jours
|
sans frais
|
| * 18 |
*Obtenir une connexion téléphonique (une ligne fixe)
|
5 jours
|
MAD 1 000
|
| 19 |
Enregistrer la construction à l’Agence Urbaine
|
7 jours
|
0,5% valeur de la construction
|
* Takes place simultaneously with another procedure.
Subnational Data
Close