Niger

Dealing with Construction Permits in

Niger

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: XOF 390,180,000
  • City: Niamey

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain legal certificate of ownership

Before the Finance Law of 2006, it was not possible to obtain a property title for undeveloped lands. A legalized copy of the deed of transfer (acte de cession) was required. In addition to the owner's copy, two additional copies are usually kept at the mayor's office. The site plan is not usually attached to the deed of transfer.

Agency: Service des Domaines
1 day XOF 1,500
2 Obtain cadastral extract (plan de situation)

The site plan is also required by the water (SEEN) and electricity (NIGELEC) companies. The site plan costs XOF 1,000 and must be accompanied by a XOF 100 stamp.

Agency: Service des Domaines
2 days XOF 1,100
3 Obtain building permit from the Municipality

The application file for a building permit is reviewed by the nine members of a commission that meets twice every month. If the commission meets the day after the file was submitted, authorization may be given that same day. Members of the commission include representatives from the tax authorities, the Ministry of Urban Planning (Ministère d’Urbanisme), the fire and safety agency (Service Sapeurs-Pompiers), and the cadastre. According to Article 17 of Order No. 59-113 (Ordonnance 59-113, Article 17), 3 copies of the following documents must be submitted: The applicants identity card Copies of the properyt title duly stamped Site plans (plan de situation) Ground plan (plan de masse) Plumping plan Electrical plan Thirty days is the legal time limit for issuance. In reality, however, the waiting time depends on the degree of follow-up. Most practitioners contact each member of the committee separately to expedite the process. Without follow-up, the permit might not be obtained within 6 months (if at all). With connections, it can be obtained in a week.

Agency: Municipality
180 days XOF 675,300
4 Receive municipal inspection at beginning of construction - I

Inspections are conducted without notification.

Agency: Municipality
1 day no charge
5 Receive municipal inspection at beginning of construction - II

Inspections are conducted without notification.

Agency: Municipality
1 day no charge
6 Re-assess the property value

In the case considered here, it is assumed that the construction value is 300,000 per square meter, that the total warehouse area is 1,300.6 square meters, and that the property value accounts for half the total project value. The new property value is equal to the initial value plus that of the construction project. The reassessment is required to be able to use the property and building as a loan guarantee.

Agency: Service des Domaines
1 day XOF 2,926,350
7 Apply for water connection

The agency in charge of the water inspection is the Water Expotaition Society of Niger (Société d’Exploitation des Eaux du Niger, SEEN). There is an application fee of XOF 1,500 and a cost associated with the pipelines used for the water connection. There are two different types of pipes: One type of pipelines has a diameter of 63 millimeters and costs XOF 88,557; the other type has a diameter of 110 millimeters and costs about XOF 134,000. It is advisable to wait for SEEN to establish a water network in the area before applying for the water connection. The cost is assumed to be the average of the estimated cost range.

Agency: Société d'Exploitation des Eaux du Niger (SEEN)
1 day no charge
8 Receive site inspection by water provider SEEN

The site visit to establish the cost estimate takes a day. In practice, it takes about 2 weeks for the inspectors to come.

Agency: Société d'Exploitation des Eaux du Niger (SEEN)
1 day no charge
9 Pay fees and obtain water connection

There is a cost associated with pipes that must be extended for the water connection. There are two different types of pipes: one type has a 63-millimeter diameter (6 meter and costs XOF 88,557; the other has a diameter of 110 millimeters and costs about XOF 134,000. It is advisable to wait for SEEN to establish a water network in the area before applying for the water connection. The average of the two estimated costs is assumed here.

Agency: Société d'Exploitation des Eaux du Niger (SEEN)
77 days XOF 111,279
* 10 Apply for fixed telephone line



Agency: Société Nigérienne des Télécommunications (SONITEL )
1 day no charge
11 Inspection by SONITEL

Inspection by the telephone company (SONITEL) occurs within 48 hours of submitting the application.

Agency: Société Nigérienne des Télécommunications (SONITEL )
1 day no charge
12 Pay fees and obtain telephone connection

If the company also leases the telephone equipment from SONITEL, the cost for the connection would be included in the monthly bill.

Agency: Société Nigérienne des Télécommunications (SONITEL )
60 days XOF 75,400
* Takes place simultaneously with another procedure.