Panama

Dealing with Construction Permits in

Panama

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: USD 429,696
  • City: Panama City

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Request and obtain Good Standing Certificate

The good-standing certificate is obtained from the Public Registry Office.

Agency: Public Registry Office
2 days USD 30
2 Request and obtain Environmental Study

The environmental impact study must be conducted by an outside independent environmental consultant, and certified by the National Environmental Authority (ANAM). In this case, given the intended use of the warehouse, the required environmental impact study is that of Type I.

The process of completing an environmental impact study may take from 15 to 30 days, but the approval by the National Environmental Authority could take approximately 45 days, depending on the category of the environmental impact study.

Agency: National Environmental Authority (ANAM)
23 days USD 700
3 Notarize affidavit



Agency: Notary
1 day USD 3
4 Submit Drawings (Anteproyecto) to the Municipality and obtain clearance

The architect must fill out the petition form and submit the preliminary design (anteproyecto). The Municipal Office has created a centralized window for filing of the preliminary project design. However, the one-stop shop does not work well, and BuildCo must follow up with each authority.

Agency: Municipal Office (Departamento de Aprobación de Planos y Permisos)
7 days USD 1
5 Consultation with the Municipality to determine approvals

A public official from the Municipal Office determines the government offices that must approve the project. Representatives of the different offices are located in the municipality, but in separate offices. The company or architect must obtain the approvals from those offices directly.

Agency: Municipal Office (Department of Approval of Blueprints and Permits)
6 days USD 370
* 6 Request and obtain signature of certified fire specialist

BuildCo must receive an approval of the project drawings related to fire safety from an independent and certified specialist. This is then submitted to the Fire Department Safety Office of the Municipal Office for approval.

Agency: Certified Fire Specialist
2 days no charge
* 7 Request and obtain preliminary approval from Fire Department Safety Office



Agency: Municipal Office (Fire Department Safety Office)
2 days no charge
* 8 Request and obtain preliminary approval from Ministry of Public Works



Agency: Municipal Office (Ministry of Public Works)
1 day USD 10
* 9 Request and obtain preliminary approval from Environmental Authority

The fee is paid at the head office of the Environmental Authority rather than at the Municipal Office.

Agency: Municipal Office (Environmental Authority)
15 days USD 350
10 Request and obtain Construction Permit

BuildCo must present the application to the director of the Municipal Construction and Works Authority, accompanied by two copies of the blueprints; the approvals issued by the Fire Department Safety Office, Ministry of Health, Ministry of Public Works, and Environmental Authority, and the municipal good standing certificate; and proof of registration of BuildCo with the Technical Board.

The cost is taken to be 1% of the project value (in this case, the warehouse value), which would vary between USD 4,266.95 and USD 422,695.

Unannounced construction permit regulation inspections may take place during construction.

Agency: Municipal Office
15 days USD 4,267
11 Request and connect to water and sewerage services



Agency: Instituto de Acueductos y Alcantarillados Nacionales
14 days USD 80
* 12 Request and connect to phone services



Agency: Cable & Wireless
3 days USD 30
* 13 Receive inspection from Fire Department Safety Office

BuildCo must receive an inspection from the Fire Department so that the department can issue a permit. Inspectors come according to a schedule of visits that is defined when the preliminary approval has been granted (Procedure 7).

Agency: Municipal Office (Fire Department Safety Office)
1 day no charge
14 Request and obtain Occupation Permit

An inspection may be carried out on the site.

Agency: Municipal Office (Fire Department Safety Office)
10 days USD 60
15 Obtain permit by Fire Department Safety Office



Agency: Municipal Office (Fire Department Safety Office)
2 days USD 230
16 Notary notarizes “Declaration of Improvement” (Declaración de Mejora)

The declaration is drafted on an official form (escritura pública).

Agency: Notary
2 days USD 100
17 Register building with the Central Property Registry



Agency: Central Property Registry
18 days USD 550
* Takes place simultaneously with another procedure.