Philippines

Ease of Doing Business in

Mandaue - Philippines

This page summarizes Doing Business data for Mandaue. The first table shows its rank among 25 cities/regions in Philippines. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.

Economy Overview

Region East Asia & Pacific
Income Category Lower middle income
Population 94,852,030
GNI Per Capita (US$) 2,210.00
Ease of Doing Business Rank among 25 cities in Philippines Top city in Philippines
n.a. n.a.
Topic Rankings Rank among 25 cities in Philippines Top city in Philippines
Starting a Business 13 General Santos
Dealing with Construction Permits 8 Davao City
Registering Property 8 Valenzuela

Subnational Data


Dealing with Construction Permits

Info

Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.

Indicator Mandaue East Asia & Pacific OECD

The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties.

View methodology
Procedures (number)
35 17 14

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.

View methodology
Time (days)
72 148 143

Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded.

View methodology
Cost (% of income per capita)
135.5 86.9 78.7
No. Procedure Time to Complete Associated Costs
1 Obtain certified true copy of the land title from the Register of Deeds (RD) 2 days PHP 57 (PHP 30 for the certification + PHP 6 for each additional page (2 pages needed) + PHP 15 documentary stamp tax)
* 2 Obtain certified true copy of the tax declaration of real property from the City Assessor's Office (CAO) 1 day PHP 37 (PHP 22 certification + PHP 15 documentary stamp tax)
* 3 Obtain lot plan with site map from the geodetic engineer 2 days PHP 1,500
* 4 Obtain barangay clearance 2 days PHP 200
5 Apply for the locational clearance at the City Planning and Development Office (CPDO) 1 day No cost
6 Notarize the locational clearance application form at the notary 1 day PHP 100
7 Receive inspection for the locational clearance from the CPDO 1 day No cost (fees included in procedure 8)
8 Obtain the locational clearance from the CPDO 2 days PHP 24,750 (PHP 5,000 + 1/10 of 1% of the total estimated cost of the project in excess of PHP 2,000,000 + 10% increase)
9 Apply for the building permit and ancillary permits at the Office of the Building Official (OBO) 1 day No cost
10 Get evaluation of and comments on the architectural plans from the OBO 1 day No cost (fees included in procedure 17)
11 Get evaluation of and comments on the civil/structural plans from the OBO 1 day No cost (fees included in procedure 17)
12 Get evaluation of and comments on the line and grade plans from the OBO 1 day No cost (fees included in procedure 17)
13 Get evaluation of and comments on the sanitary and plumbing plans from the OBO 1 day No cost (fees included in procedure 17)
14 Get evaluation of and comments on the electrical plans from the OBO 1 day No cost (fees included in procedure 17)
15 Apply and obtain Fire Safety Evaluation Clearance (FSEC) from the local Fire Marshall at the Bureau of Fire Protection (BFP) 7 days PHP 19,500 (0.1% of estimated project cost)
16 Obtain the Mayor’s clearance from the City Mayor's Office (CMO) 1 day No cost (fees included in procedure 17)
17 Obtain the building permit from the OBO 8 days PHP 39,018 (according to the National Building Code of the Philippines, the cost of the building permit is PHP 23 per square meter. The computation here is based on PHP 30 per square meter to account for ancillary costs such as electrical, mechanical and plumbing fees)
18 Receive inspection from the BFP during construction 1 day No cost (fees included in procedure 15)
19 Receive inspection from the OBO during construction 1 day No cost (fees included in procedure 17)
20 Apply for the Certificate of Occupancy and Certificate of Final Electrical Inspection (CFEI) at the OBO 1 day No cost
21 Apply for the Fire Safety Inspection Certificate (FSIC) at the BFP 1 day PHP 3,901 (10% of building permit fees)
22 Receive final inspection for the FSIC from the BFP 1 day No cost (fees included in procedure 21)
23 Obtain the FSIC from the BFP 3 days No cost
24 Receive final inspection for the Certificate of Occupancy and CFEI from the OBO 1 day No cost (fees included in procedure 25)
25 Obtain the Certificate of Occupancy and CFEI from the OBO 10 days PHP 19,000 (PHP 1,000 for the first PHP 1,200,000 of the project value; PHP 1,000 for every PHP 1,000,000 in excess thereof. If excess is less than PHP 500,000, there is no charge; but if more than PHP 500,000, the cost is PHP 1,000)
26 Apply for electricity connection at Visayan Electric Company (VECO) 1 day No cost
27 Receive inspection for electricity connection from VECO 1 day No cost
28 Obtain electricity connection from VECO 19 days No cost
* 29 Apply for water connection at Metro Cebu Water District (MCWD) 1 day PHP 4,950 (installation fee paid during application)
* 30 Receive inspection for water connection from MCWD 1 day No cost
* 31 Obtain water connection from MCWD 15 days No cost
* 32 Obtain telephone connection from the telephone company 5 days No cost
* 33 Apply for the tax declaration of improvement at the CAO 1 day No cost
* 34 Receive inspection from the Appraiser of CAO 1 day No cost
* 35 Obtain the tax declaration of improvement from the CAO 1 day No cost
* Takes place simultaneously with another procedure.