São Tomé and Príncipe

Dealing with Construction Permits in

São Tomé and Príncipe

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: STD 9,996,535,028
  • City: São Tomé

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Request and obtain approval of construction from the Directorate of Urbanism and Public Constructions

BuildCo should be registered officially with the the Directorate of Public Constructions (Direcção de Obras Públicas-DOP) from the Ministry of Public Constructions and Natural Resources as a building company and have a permission to operate as such (Alvará para empreitada de construção e obras públicas)
The company needs to submit a request for the approval of construction that should include:
-the design of the project by the architect
- details of the engineering structures
- electricity network details
- water sources
- water and waste management plans

Agency: Directorate of Urbanism and Public Constructions
20 days USD 4
2 Request and obtain location map from Geographic Services

BuildCo needs to obtain a location map (croquis) of the land.

Agency: Geographic Services
5 days USD 4
3 Request and obtain certification of route measuring from Geographic Services

Additionally, the company would need to request that the project to be built is approved by the Geographic Services, as to verify that it can be built and it is according to the city limits, and ocean limits.

Agency: Geographic Services
5 days USD 10
4 Request and obtain construction authorization from Geographic Services

Geographic Services of the Cadastre measures the terrain and verifies whether the project is feasible on that particular plot of land.

Agency: Geographic Services
15 days USD 75
5 Request and obtain project approval from the Directorate of Urbanism and Public Construction

The Engineering Association is part of the Directorate of Urbanism and Public Construction. Approval from the Engineering Association is thus also requested and obtained at this point.

Agency: Directorate of Urbanism and Public Constructions
7 days USD 60
6 Random inspection I



Agency: Directorate of Urbanism and Public Constructions
1 day no charge
7 Random inspection II



Agency: Directorate of Urbanism and Public Constructions
1 day no charge
8 Request water connection

The time line can vary, depending on the availability of utility networks in the vicinity of the construction site. Utility networks are not available everywhere in the country. In most nonresidential areas, for example, obtaining water or electricity connections is time consuming. Investors thus opt for developing their own water supply and sewage system, and use a generator for electricity.

Empresa de Agua e Electricidade (EMAE) is the local provider of electricity and water.

Agency: Empresa de Agua e Electricidade (EMAE)
1 day USD 80
9 Receive inspection for water



Agency: Empresa de Agua e Electricidade (EMAE)
38 days USD 28
10 Connect to water services



Agency: Empresa de Agua e Electricidade (EMAE)
70 days no charge
11 Request and connect to phone services



Agency: Companhia Santomense de Telecomunicacoes SARL
5 days USD 30
12 Request and receive final inspection from the Directorate of Urbanism and Public Construction



Agency: Directorate of Urbanism and Public Constructions
13 days USD 292
13 Register building with a Notary

The company has to register the new construction with a notary.
The cost is 1% of the warehouse value.

Agency: Real Estate Registry
30 days USD 5,860