Dealing with Construction Permits in
Senegal
Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections.
The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.
-
Building a warehouse
-
Estimated Warehouse Value:
XOF 150,000,000
- City: Dakar
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Obtain property title documents (certificats de droit réel ou réquisition)
The property title documents include the history of the property and all loans associated with it.
Agency: Land Authorities (Bureau de la Conservation Foncière (Service des Domaines))
|
5 days
|
XOF 600
|
| 2 |
Obtain zoning certificate (Certificat d’Urbanisme)
The zoning certificate outlines the zoning regulations concerning the property.
Agency: Regional urban planning authority (Service Régionale d’Urbanisme )
|
10 days
|
XOF 1,500
|
| 3 |
Obtain building permit
The application file is submitted in five copies. Each copy consists of an application form, along with the following: - Plans of all the levels and facades at a scale of 1:100. - Block and location plan. - Two copies of the property title (per application).
Agency: Ministry of Urbanism and Town Planning; Inspection Office; City Hall; Land Management; Hygiene Service; Civil Safety Office
|
90 days
|
XOF 206,000
|
| 4 |
Hire a private inspection agency and receive approval of the technical execution plan
It is rare to receive an inspection from the authorities. Thus, to ensure that building standards are met, BuildCo hires a private inspection agency. Private inspectors visit the site at least once a week to perform technical inspections.
Agency: Bureau de Control
|
1 day
|
XOF 1,500,000
|
| 5 |
Request final inspection from the Service d'Urbanisme to receive certificate of conformity
Once construction is completed, BuildCo must fill out a form asking for a certificate of conformity (certificat de conformite). A representative from BuildCo must go to the Service Regional in person with a copy of the authorized plans.
Agency: Regional urban planning authority (Service Régionale d’Urbanisme )
|
1 day
|
XOF 5,500
|
| 6 |
Receive final inspection
This is an inspection to verify compliance of the construction works with the regulations (prior to delivery of the certificate of compliance). Sometimes, companies have to wait 2 weeks before receiving this final inspection
Agency: Inspection agency (Direction Régionale de l’Urbanisme et de l’Architecture)
|
1 day
|
no charge
|
| 7 |
Obtain certificate of completion
The declaration of completion of construction (déclaration attestant de l’achèvement des travaux) must be submitted within 30 days from the date of the end of construction activities.
Agency: Urban Service (Service de l’Urbanisme)
|
10 days
|
no charge
|
| * 8 |
Apply for sewage connection
Agency: Office National d’Assainissement du Sénégal
|
1 day
|
no charge
|
| 9 |
Apply for water connection
BuildCo must apply for the connection at the private water company, SDE. They lack personnel and so the time to obtain the estimate (devis) for the payment of fees takes about 1 to 2 weeks.
Agency: Société Sénégalaise des Eaux (SDE)
|
1 day
|
no charge
|
| * 10 |
Receive sewage inspection
BuildCo must go the sewage company to retrieve the inspectors for the inspection of the sewage mains. Otherwise, it can take them a few weeks to come. An inspection is necessary to obtain the estimate (devis) for the works to be completed.
Agency: Office National d’Assainissement du Sénégal
|
1 day
|
no charge
|
| * 11 |
Pay the fees and obtain sewage connection
ONAS inspectors prepare the quotation (devis) within a week of inspecting the site. BuildCo must then go to ONAS to sign the paperwork and pay the fees. After that, they come and install the connection. ONAS may sometimes outsource works to a private company.
Agency: Office National d’Assainissement du Sénégal
|
90 days
|
XOF 250,000
|
| * 12 |
Pay the fees and obtain water connection
The application form costs from XOF 14,000 to XOF 20,000. The connection cost is around XOF 115,000 for industrial companies. This cost increases if the building is distant from the nearest source of water.
Agency: Société Sénégalaise des Eaux (SDE)
|
28 days
|
XOF 135,000
|
| * 13 |
Obtain phone connection
Agency: SONATEL
|
7 days
|
XOF 45,000
|
* Takes place simultaneously with another procedure.